Times House and Laundry Buildings (4-6 Bravingtons Walk, 8 Caledonia Street and part ground floor area of 3 Bravingtons Walk), Laundry Yard and part of Caledonia Street, Regent Quarter, Kings Cross, London N1,

Full / Other PlanningCaledonian ward
Submission
3 Aug 2021
Target
2 Nov 2021
Decision
20 Dec 2022
Outcome
Approved
Committee decisionApproved
20 Dec 2022
Determined by the planning committee
Loading map…
Scheme description

Refurbishment of existing buildings; partial demolition and infill extensions to the southern, northern courtyard and western elevations at ground, first, second, third and fourth floor level and one storey roof extensions to provide additional Class E(g)(i) Office floorspace at Times House; removal of plant room and entrance, alteration to the elevations and enlargement of existing windows to Laundry Building; further works include the provision of three flexible Food and Drink (Class E (b)) and/or Bar/Drinking Establishment (Sui Generis) units, and four Retail (Class E (a)) units at ground floor level; provision of outdoor terraces at first, fourth and fifth floor levels, basement cycle st

Parties
Applicant
Endurance Land LLP
Timeline
3 Aug 2021
Application submitted
13 Aug 2021
Application validated
20 Dec 2022
Committee decision: Approved
Supporting documents · 180
125 of 180
Area Schedule - Laundry Building RevF3 Nov 2021View ↗
Dwg 13601-A-Z2-LXX-07-200-P1 - Proposed North Elevation4 Nov 2021View ↗
Dwg 13601-A-Z2-LXX-07-160-P1 - Proposed Context Section Nort4 Nov 2021View ↗
Dwg 13601-A-Z2-LXX-07-104-P1 - Proposed Fourth Floor Plan4 Nov 2021View ↗
Area Schedule Times House-Stage034 Nov 2021View ↗
Dwg 13601-A-Z2-LXX-07-105-P1 - Proposed Fifth Floor Plan4 Nov 2021View ↗
Area Schedule Laundry Building-Stage034 Nov 2021View ↗
Heritage Statement Update Part 13 Nov 2021View ↗
MKA Ecology-Regents Quarter-Bat Mitigation Close Down Report9 Dec 2021View ↗
Application Form12 Aug 2021View ↗
Planning Statement12 Aug 2021View ↗
Geoenvironmental and Geotechnical Report Part138 Aug 2021View ↗
Geoenvironmental and Geotechnical Report Part118 Aug 2021View ↗
Geoenvironmental and Geotechnical Report Part108 Aug 2021View ↗
Public Realm Report_BlockB_THLB_Publica_Part78 Aug 2021View ↗
Air Quality Assessment8 Aug 2021View ↗
Public Realm Report_BlockB_THLB_Publica_Part18 Aug 2021View ↗
Geoenvironmental and Geotechnical Report Part78 Aug 2021View ↗
Public Realm Report_BlockB_THLB_Publica_Part58 Aug 2021View ↗
Geoenvironmental and Geotechnical Report Part128 Aug 2021View ↗
Geoenvironmental and Geotechnical Report Part98 Aug 2021View ↗
Proposed Sections & Elevations8 Aug 2021View ↗
Geoenvironmental and Geotechnical Report Part88 Aug 2021View ↗
Geoenvironmental and Geotechnical Report Part68 Aug 2021View ↗
Geoenvironmental and Geotechnical Report Part18 Aug 2021View ↗
View Application Page ↗
Data from the Islington planning register.
Summary
Reference
P2021/2269/FUL
Type
Full Planning Application
Applicant
Endurance Land LLP
Submitted
3 Aug 2021
Decision date
20 Dec 2022
Council
Decision
Approved
Decision route
Committee
How long, really
72
wks · this application
Submission → decision · 64 wks over the 8-week target