Planning Application
2025/01746/FUL
13 And 15 Tournay Road London SW6 7UG
Full / Other PlanningWalham Green ward
Submission
25 Jun 2025
Target
9 Oct 2028
Decision
9 Oct 2025
Outcome
Approved
Delegated decisionApproved
9 Oct 2025Decided by Hasna Miah under delegated powers
Loading map…
Scheme description
Erection of a single storey rear extension to the side of the existing back addition, installation of 3no. rooflights in the front roofslope following the removal of 2no. existing rooflights, raising the height of the first floor back addition parapet wall by 200mm, installation of 1no. air conditioning unit above the flat roof of first floor back addition to no. 13; installation of new sliding doors to replace the existing doors and window to the rear elevation at ground floor level to nos. 13 and 15; refurbishment of the existing single storey side infill roof, and raising the cill of 1no. window to the rear elevation at first floor level to no. 15.
Parties
Timeline
25 Jun 2025
Application submitted
11 Aug 2025
Application validated
9 Oct 2025
Delegated decision: Approved
Supporting documents · 16
DESIGN-AND-ACCESS-STATEMENT-REV-C-16062025View ↗
FLOOD-RISK-ASSESSMENT-REV-B-16122021View ↗
15-D-PROPOSED-SF-PLAN-24052022View ↗
14-C-PROPOSED-FF-PLAN-12052022View ↗
13-D-PROPOSED-GF-PLAN-12052025View ↗
02-A-EXISTING-AND-PROPOSED-BLOCK-PLAN-16062025View ↗
01-A-LOCATION-PLAN-22102021View ↗
16-B-PROPOSED-TF-PLAN-26102021View ↗
17-D-PROPOSED-REAR-ELEVATION-12052022View ↗
18-C-PROPOSED-SIDE-ELEVATION-10052022View ↗
19-A-PROPOSED-FRONT-ELEVATION-26102021View ↗
20-B-PROPOSED-ROOF-PLAN-26052022View ↗
APPLICATIONFORMREDACTEDView ↗
13-AND-15-TOURNAY-ROAD---EXISTING-SURVEY-CView ↗
PER.FULL-PLANNING-PERMISSIONView ↗
DELEGATED-REPORT-TEMPLATE---LIVEView ↗
View Application Page ↗
Data from the Hammersmith And Fulham planning register.
Summary
Reference
2025/01746/FUL
Ward
Type
Full Planning Application
Applicant
Mrs A Horn
Submitted
25 Jun 2025
Decision date
9 Oct 2025
Officer
Council
Decision
Approved
Decision route
—
How long, really
15
wks · this application
Submission → decision · 7 wks over the 8-week target