Development Intent
Planning AtlasHammersmith And FulhamGroveApplication
Planning Application

2023/02993/FUL

6 Carthew Road London W6 0DX

Full / Other PlanningGrove ward
Submission
15 Nov 2023
Target
2 Feb 2027
Decision
2 Feb 2024
Outcome
Approved
Delegated decisionApproved
2 Feb 2024
Decided by Paul Curtis under delegated powers
Loading map…
Scheme description

Erection of a front and rear roof extension; erection of a rear extension at first floor level, over part of the proposed single storey rear extension; erection of a single storey rear extension, following the demolition of existing back addition; raising the height of an existing front party wall to adjoining neighbour at no.4, to match existing adjoining neighbour at no.8; erection of new side flank walls to the rear elevation, to match adjoining neighbour at no.8.

Parties
Applicant
Mr Robert Mumby
Ward
Grove
Timeline
15 Nov 2023
Application submitted
22 Nov 2023
Application validated
2 Feb 2024
Delegated decision: Approved
Supporting documents · 22
188_001REVB-EXISTING-PLANSView ↗
188_002REVA-EXISTING-ELEVATIONSView ↗
188_120REVA-PROP-GROUND-FIRSTView ↗
188_DA_01-DESIGN-AND-ACCESS--and--FLOOD-RISK-ASSESSMENTView ↗
188_122-PROPOSED-FRONT-REAR-ELEV-SECTIONSAA_BBView ↗
188_PH_01-PHOTO-SHEET-01View ↗
188_PH_03-PHOTO-SHEET-03View ↗
188_PH_02-PHOTO-SHEET-02View ↗
188_121-PROPOSED-SECOND-ROOF-PLANSView ↗
188_OS_01-ORDNANCE-SURVEY-MAP-1TO1250View ↗
188_OS_02-BLOCK-PLAN-EXISTINGView ↗
188_OS_03-BLOCK-PLAN-PROPOSEDView ↗
FLOOD-MAPView ↗
188_001REVC-EXISTING-PLANSView ↗
188_002REVB-EXISTING-ELEVATIONS-SECTIONSView ↗
188_120-REVB-PROPOSED-GROUND-FIRST-PLANView ↗
188_122REVD-PROPOSED-ELEVATIONS-SECTIONSView ↗
DESIGN--and--ACCESS-STATEMENT-INCLUDING-FLOOD-RISK-ASSESSMENView ↗
DA-REV-BView ↗
GROUND-FLOOR-PLANView ↗
PROPOSED-ELEVATIONSView ↗
PER.FULL-PLANNING-PERMISSIONView ↗
View Application Page ↗
Data from the Hammersmith And Fulham planning register.
Summary
Reference
2023/02993/FUL
Ward
Type
Full Planning Application
Applicant
Mr Robert Mumby
Submitted
15 Nov 2023
Decision date
2 Feb 2024
Decision
Approved
Decision route
How long, really
11
wks · this application
Submission → decision · 3 wks over the 8-week target