2023/01608/FUL

53B Rosebury Road London SW6 2NQ

Full / Other PlanningSands End ward
Submission
19 Jun 2023
Target
5 Sep 2026
Decision
5 Sep 2023
Outcome
Approved
Delegated decisionApproved
5 Sep 2023
Decided by Mwansa Tembo under delegated powers
Loading map…
Scheme description

Excavation of part of the front garden to form a lightwell and lowering of the existing basement floor in connection with the enlargement of the existing basement; installation of a door and window at basement level to the front elevation; demolition of the front boundary wall, erection of railings and entrance gate to the front boundary.

Parties
Applicant
Oliver Gordon
Timeline
19 Jun 2023
Application submitted
28 Jun 2023
Application validated
5 Sep 2023
Delegated decision: Approved
Supporting documents · 37
125 of 37
2223-007_110_P04View ↗
2223-007_111_P04View ↗
2223-007_120_P06View ↗
2223-007_121_P03View ↗
2223-007_122_P03View ↗
2223-007_150_P01View ↗
2223-007_CILView ↗
EMAIL-WITH-DWGSView ↗
2223-007_001View ↗
2223-007_010-(EXISTING)View ↗
2223-007_011-(EXISTING)View ↗
2223-007_020-(EXISTING)View ↗
2223-007_021-(EXISTING)View ↗
2223-007_022-(EXISTING)View ↗
2223-007_FLOOD-RISK-ASSESSMENTView ↗
BASEMENT-CONSTRUCTION-METHOD-DRAWINGView ↗
2223-007_110-(APPROVED-SCHEME)View ↗
2223-007_111-(APPROVED-SCHEME)View ↗
2223-007_120-(APPROVED-SCHEME)View ↗
2223-007_121-(APPROVED-SCHEME)View ↗
2223-007_122-(APPROVED-SCHEME)View ↗
OFFICER-S-FILE-NOTEView ↗
2223-007_150_P01-PROPOSED-FRONT-ELEVATIONView ↗
View Application Page ↗
Data from the Hammersmith And Fulham planning register.
Summary
Reference
2023/01608/FUL
Type
Full Planning Application
Applicant
Oliver Gordon
Submitted
19 Jun 2023
Decision date
5 Sep 2023
Decision
Approved
Decision route
How long, really
11
wks · this application
Submission → decision · 3 wks over the 8-week target