Planning Application
2022/02582/FUL
64 Crabtree Lane London SW6 6LW
Full / Other PlanningFulham Reach ward
Submission
8 Sep 2022
Target
8 Feb 2026
Decision
8 Feb 2023
Outcome
Approved
Delegated decisionApproved
8 Feb 2023Decided by Mwansa Tembo under delegated powers
Loading map…
Scheme description
Erection of a rear roof extension; replacement of fenestration to the front and rear elevation; alterations at ground floor level to the entrance on Crabtree Lane; repoint brick work and replace main roof and back addition roof tiles.
Parties
Timeline
8 Sep 2022
Application submitted
20 Sep 2022
Application validated
8 Feb 2023
Delegated decision: Approved
Supporting documents · 45
1–25 of 45
A_1403_DEMOLITION-ROOF-PLANView ↗
A_1501_DEMOLITION-CRABTREE-LANE-(SOUTH)-ELEVATIONView ↗
A_1401_DEMOLITION-FIRST-FLOOR-PLANView ↗
A_2002_PROPOSED-LOFT-PLANView ↗
A_2003_PROPOSED-ROOF-PLANView ↗
A_0200_LOCATION-PLANView ↗
A_2200_PROPOSED-SECTION-A-AView ↗
A_1601_DEMOLITION-SECTION-B-BView ↗
A_2100_PROPOSED-PETLEY-ROAD-(EAST)-ELEVATIONView ↗
A_2101_PROPOSED-CRABTREE-LANE-(SOUTH)-ELEVATION-(MANSARD)-45View ↗
A_1402_DEMOLITION-LOFT-PLANView ↗
A_2101_PROPOSED-CRABTREE-LANE-(SOUTH)-ELEVATIONView ↗
A_2201_PROPOSED-SECTION-B-BView ↗
A_1600_DEMOLITION-SECTION-A-AView ↗
220831-PLANNING-STATEMENT-64-CRABTREE-ROAD-FINAL-SUBMITTEDView ↗
A_0701_EXISTING-CRABTREE-LANE-(SOUTH)-ELEVATIONView ↗
A_2000_PROPOSED-GROUND-FLOOR-PLANView ↗
22016_64-CRABTREE-LANE_DAS_PART-1View ↗
A_0800_EXISTING-SECTION-A-AView ↗
A_0601_EXISTING-FIRST-FLOOR-PLANView ↗
A_2001_PROPOSED-FIRST-FLOOR-PLANView ↗
220907-COVERING-LETTER-64-CRABTREE-LANEView ↗
A_0801_EXISTING-SECTION-B-BView ↗
A_1500_DEMOLITION-PETLEY-ROAD-(EAST)-ELEVATIONView ↗
A_1400_DEMOLITION-GROUND-FLOOR-PLANView ↗
View Application Page ↗
Data from the Hammersmith And Fulham planning register.
Summary
Reference
2022/02582/FUL
Ward
Type
Full Planning Application
Applicant
Mr and Mrs Kendrick
Submitted
8 Sep 2022
Decision date
8 Feb 2023
Officer
Council
Decision
Approved
Decision route
—
How long, really
22
wks · this application
Submission → decision · 14 wks over the 8-week target