Planning Application

21/00274/FUL

Riddlesdown Car Park Riddlesdown Road Purley CR8 1DF

Full / Other PlanningPurley Oaks And Riddlesdown wardArchaeological Priority Area: Name: London to Brighton Roman
Submission
20 Jan 2021
Target
29 Mar 2021
Decision
4 Jan 2022
Outcome
Approved
Committee decisionApproved
4 Jan 2022
Determined by the planning committee
Loading map…
Scheme description

Installation of 2 x 500mm x 500mm x 500mm concrete plinths for the erection of 2 x Hectronic Citea car park ticketing machines Erection of 2 x pole for the siting of ANPR cameras and associated signages, poles and wooden structures (retrospective) (revised description to cover all works undertaken).

Parties
Applicant
Hadyn Robson
Agent
Timeline
20 Jan 2021
Application submitted
1 Feb 2021
Application validated
4 Jan 2022
Committee decision: Approved
Supporting documents · 19
GRANTED (PG) FULL - DEC NOTICE4 Jan 2022View ↗
OFFICER REPORT WEB - FINAL4 Jan 2022View ↗
ITEM 5.1 RIDDLESDOWN CAR PARK PURLEY27 Oct 2021View ↗
REVISED28 May 2021View ↗
REQUESTED28 May 2021View ↗
REQUESTED28 May 2021View ↗
REQUESTED28 May 2021View ↗
REQUESTED28 May 2021View ↗
SITE NOTICE NEIGHBOUR NOTIFICATION28 May 2021View ↗
SITE NOTICE NEIGHBOUR NOTIFICATION19 Feb 2021View ↗
SITE NOTICE NEIGHBOUR NOTIFICATION1 Feb 2021View ↗
SITE PHOTOS31 Jan 2021View ↗
CAR PARK MACHINE SPECIFICATION31 Jan 2021View ↗
APPLICATION FORM REDACTED20 Jan 2021View ↗
RIDDLESDOWN CAR PARK TICKET MACHINE LOCATIONS - AERIAL IMAGE20 Jan 2021View ↗
RIDDLESDOWN CAR PARK TICKET MACHINE LOCATIONS20 Jan 2021View ↗
4_METER_ROOT_MOUNT_COLUMN20 Jan 2021View ↗
FOUNDATION PREPARATION DIAGRAM20 Jan 2021View ↗
MACHINE DIMENSIONS20 Jan 2021View ↗
View Application Page ↗
Data from the Croydon planning register.
Summary
Reference
21/00274/FUL
Type
Full planning permission
Applicant
Hadyn Robson
Submitted
20 Jan 2021
Decision date
4 Jan 2022
Council
Decision
Approved
Decision route
Committee
How long, really
50
wks · this application
Submission → decision · 42 wks over the 8-week target
Public response
Objections
14
In support
0
Total comments
14