How long does a decision actually take?

Every application has a statutory eight-week clock. This measures real timelines from receipt to decision, by borough and application type.

Loading map…
Decision time: Full planning
11
weeks median
|
74
days

Measured from receipt to decision across 135,073 full planning applications in London. The distribution below shows how many applications fall into each time band.

Decision time distribution
maxmid0<8 weeks23,2088–13 weeks61,53813–26 weeks31,63626–52 weeks12,48052+ weeks6,211

Five time bands show the distribution of decision timelines across 135,073 full planning applications.

Coverage & scope

Discretionary, consultable applications only: full planning, householder, outline, listed building consent, reserved matters. Excludes permitted development, prior approval, lawful-development certificates, condition discharge and tree works (automatic or non-consultable).

Current view: Full planning135,073 applications tracked. Median: 74 days (11 weeks).

Related — follow the thread
The Delegation Gap
Which decisions go to officers or committee
Open →
The Objection Effect
How outcomes vary with recorded objections