Planning Application

25/09350/FULL

Hyde Park Serpentine Road London W2 2UH

Full / Other PlanningHyde Park ward
Submission
24 Dec 2025
Target
25 Mar 2026
Decision
4 Jun 2026
Outcome
Approved
Delegated decisionApproved
4 Jun 2026
Decided by Tristan Goldsmid under delegated powers
Loading map…
Scheme description

Use of the Parade Ground area of Hyde Park for the British Summer Time Concert event, including associated structures, for a temporary two year period between: 25 June 2026 and 12 July 2026 with site set up and clearance between 3 June 2026 and 23 July 2026; and 24 June 2027 and 11 July 2027 with site set up and clearance between 2 June 2027 and 22 July 2027.

Parties
Applicant
Not disclosed
Agent
Turley
Timeline
24 Dec 2025
Application submitted
4 Jun 2026
Delegated decision: Approved
Supporting documents · 74
125 of 74
GRANT OF FULL PP [PE]4 Jun 2026View ↗
DELEGATED REPORT4 Jun 2026View ↗
ECNSLT-INTERNAL CONSULTS27 Apr 2026View ↗
DAY 1 INSTALLS22 Apr 2026View ↗
PERIMETER BALLASTING & SCANNING22 Apr 2026View ↗
PARADE GROUND EVENT SITE RISK ZONES22 Apr 2026View ↗
TRP ARBORICULTURAL POLICY: TREES AND EVENTS22 Apr 2026View ↗
2ND RESPONSE FROM GARDENS TRUST13 Apr 2026View ↗
NATURAL ENGLAND RESPONSE27 Mar 2026View ↗
CNSLT-LA SOC (AMENDMENTS)26 Mar 2026View ↗
CNSLT-LA SOCIETY26 Mar 2026View ↗
ECNSLT-STD EXT CONSULTEES26 Mar 2026View ↗
HERITAGE STATEMENT25 Mar 2026View ↗
ECNSLT-STD EXT CONSULTEES18 Mar 2026View ↗
LOCAL FLOOD AUTHORITY2 Mar 2026View ↗
GARDENS TRUST COMMENT2 Mar 2026View ↗
DESIGN AND ACCESS STATEMENT25 Feb 2026View ↗
ACK-GENERAL LETTER (G/P/C)18 Feb 2026View ↗
ECNSLT-INTERNAL CONSULTS18 Feb 2026View ↗
ECNSLT-INTERNAL CONSULTS18 Feb 2026View ↗
ECNSLT-INTERNAL CONSULTS18 Feb 2026View ↗
ECNSLT-STD EXT CONSULTEES18 Feb 2026View ↗
ECNSLT-STD EXT CONSULTEES18 Feb 2026View ↗
ECNSLT-STD EXT CONSULTEES18 Feb 2026View ↗
CNSLT-LA SOCIETY18 Feb 2026View ↗
View Application Page ↗
Data from the Westminster planning register.
Summary
Reference
25/09350/FULL
Type
Full Planning Permission Application
Applicant
Not disclosed
Submitted
24 Dec 2025
Decision date
4 Jun 2026
Decision
Approved
Decision route
Delegated (officer)
How long, really
23
wks · this application
Submission → decision · 15 wks over the 8-week target
Public response
Objections
0
In support
0
Total comments
1