Planning Application
25/08069/FULL
Flat 5 6 West Halkin Street London SW1X 8JA
Full / Other PlanningKnightsbridge & Belgravia ward
Submission
5 Nov 2025
Target
12 Jan 2026
Decision
12 Mar 2026
Outcome
Approved
Delegated decisionApproved
12 Mar 2026Decided by Zulekha Hosenally under delegated powers
Loading map…
Scheme description
Alterations to existing flat roof at rear third floor level to form a roof terrace, raising of the parapet, installation of decking and replacement of window with a door at rear third floor level.
Parties
Timeline
5 Nov 2025
Application submitted
17 Nov 2025
Application validated
12 Mar 2026
Delegated decision: Approved
Supporting documents · 33
1–25 of 33
GRANT OF FULL PP [PE]12 Mar 2026View ↗
DELEGATED REPORT12 Mar 2026View ↗
DRAWING ISSUE SHEET4 Mar 2026View ↗
GLAZING DETAILS4 Mar 2026View ↗
PROPOSED THIRD FLOOR PLAN4 Mar 2026View ↗
PROPOSED SECTION4 Mar 2026View ↗
PROPOSED ELEVATION4 Mar 2026View ↗
PROPOSED ELEVATIONS4 Mar 2026View ↗
ACK-GENERAL LETTER (G/P/C)17 Nov 2025View ↗
NEIGHBOUR NOTIFICATION LETTER (21D)17 Nov 2025View ↗
SITE NOTICE 21 OR 28 DAYS IF T&C APPL.17 Nov 2025View ↗
CNSLT-LA SOCIETY17 Nov 2025View ↗
CNSLT-LA SOCIETY17 Nov 2025View ↗
CNSLT-LA SOCIETY17 Nov 2025View ↗
ECNSLT-INTERNAL CONSULTS17 Nov 2025View ↗
RECEIPT OF APPLICATION11 Nov 2025View ↗
1ST INVALID LETTER11 Nov 2025View ↗
APPLICATIONFORMREDACTED5 Nov 2025View ↗
LOCATIONPLAN5 Nov 2025View ↗
SITELOCATION5 Nov 2025View ↗
DESIGN AND ACCESS STATEMENT5 Nov 2025View ↗
DEMOLITION THIRD FLOOR PLAN5 Nov 2025View ↗
EXISTING FRONT AND DEMOLITION REAR ELEVATIONS5 Nov 2025View ↗
EXISTING AND PROPOSED SECTION THROUGH ROOF DOOR5 Nov 2025View ↗
EXISTING THIRD FLOOR PLAN5 Nov 2025View ↗
View Application Page ↗
Data from the Westminster planning register.
Summary
Reference
25/08069/FULL
Type
Full Planning Permission Application
Applicant
Ms Adamopoulos
Submitted
5 Nov 2025
Decision date
12 Mar 2026
Officer
Council
Decision
Approved
Decision route
Delegated (officer)
How long, really
18
wks · this application
Submission → decision · 10 wks over the 8-week target
Public response
Objections
0
In support
0
Total comments
0