25/07062/FULL

10 Nottingham Place London W1U 5ND

Full / Other PlanningMarylebone ward
Submission
1 Oct 2025
Target
26 Nov 2025
Decision
24 Apr 2026
Outcome
Approved
Delegated decisionApproved
24 Apr 2026
Decided by Rattan Sehra under delegated powers
Loading map…
Scheme description

Installation of two external air source heat pumps located behind the parapet walls at fourth-floor level.

Parties
Applicant
Not disclosed
Timeline
1 Oct 2025
Application submitted
24 Apr 2026
Delegated decision: Approved
Supporting documents · 36
125 of 36
GRANT OF FULL PP [PE]24 Apr 2026View ↗
DELEGATED REPORT24 Apr 2026View ↗
ACOUSTIC ASSESSMENT REPORT20 Mar 2026View ↗
EXISTING SECTION20 Mar 2026View ↗
EXISTING ROOF PLAN20 Mar 2026View ↗
EXISTING FRONT AND REAR ELEVATIONS20 Mar 2026View ↗
PROPOSED ASHP SECTION20 Mar 2026View ↗
PROPOSED ASHP ROOF PLAN20 Mar 2026View ↗
PROPOSED ASHP SECTION LINE OF SIGHT20 Mar 2026View ↗
PROPOSED ASHP LOCATION20 Mar 2026View ↗
PROPOSED ASHP ELEVATION20 Mar 2026View ↗
PROPOSED ASHP ELEVATION20 Mar 2026View ↗
LEAD LOCAL FLOOD AUTHORITY COMMENT14 Oct 2025View ↗
ACK-GENERAL LETTER (G/P/C)9 Oct 2025View ↗
ECNSLT-INTERNAL CONSULTS9 Oct 2025View ↗
ECNSLT-INTERNAL CONSULTS9 Oct 2025View ↗
CNSLT-LA SOCIETY9 Oct 2025View ↗
SITE NOTICE 21 OR 28 DAYS IF T&C APPL.9 Oct 2025View ↗
NEIGHBOUR NOTIFICATION LETTER (21D)9 Oct 2025View ↗
RECEIPT OF APPLICATION7 Oct 2025View ↗
APPLICATIONFORMREDACTED1 Oct 2025View ↗
FEECALCULATION1 Oct 2025View ↗
ATTACHMENTSUMMARY1 Oct 2025View ↗
PROPOSED ASHP LOCATION 7239-CAL-ASHP-LOC REV.01 Oct 2025View ↗
PROPOSED FRONT AND REAR ELEVATION 7239-CAL-ASHP-ELV REV.01 Oct 2025View ↗
View Application Page ↗
Data from the Westminster planning register.
Summary
Reference
25/07062/FULL
Type
Full Planning Permission Application
Applicant
Not disclosed
Submitted
1 Oct 2025
Decision date
24 Apr 2026
Decision
Approved
Decision route
Delegated (officer)
How long, really
29
wks · this application
Submission → decision · 21 wks over the 8-week target
Public response
Objections
4
In support
0
Total comments
5