Planning Application

25/05461/FULL

1B - 1C Tottenham Court Road London W1T 1BB

Full / Other PlanningWest End ward
Submission
4 Aug 2025
Target
11 Nov 2025
Decision
25 Mar 2026
Outcome
Approved
Delegated decisionApproved
25 Mar 2026
Decided by Sanchita Raghunathan under delegated powers
Loading map…
Scheme description

Replacement air source heat pumps to rear fourth floor flat roof, and glazing adjustments to windows. (Linked to 25/04604/LBC)

Parties
Applicant
Mr F Simsek
Timeline
4 Aug 2025
Application submitted
16 Sep 2025
Application validated
25 Mar 2026
Delegated decision: Approved
Supporting documents · 34
125 of 34
GRANT OF FULL PP [PE]25 Mar 2026View ↗
DELEGATED REPORT25 Mar 2026View ↗
MECHANICAL PROPOSALS25 Nov 2025View ↗
FOURTH FLOOR AND ROOF PLAN - PROPOSED25 Nov 2025View ↗
THIRD FLOOR PLAN - PROPOSED25 Nov 2025View ↗
SECOND FLOOR PLAN - PROPOSED25 Nov 2025View ↗
FIRST FLOOR PLAN - PROPOSED25 Nov 2025View ↗
ACK-GENERAL LETTER (G/P/C)22 Sep 2025View ↗
CNSLT-LA SOCIETY22 Sep 2025View ↗
CNSLT-LA SOCIETY22 Sep 2025View ↗
SITE NOTICE 21 OR 28 DAYS IF T&C APPL.22 Sep 2025View ↗
NEIGHBOUR NOTIFICATION LETTER (21D)22 Sep 2025View ↗
ROOF PLANT DETAILS16 Sep 2025View ↗
WINDOW PROPOSALS16 Sep 2025View ↗
2ND INVALID LETTER8 Sep 2025View ↗
NOISE IMPACT ASSESSMENT3 Sep 2025View ↗
RECEIPT OF APPLICATION12 Aug 2025View ↗
1ST INVALID LETTER12 Aug 2025View ↗
APPLICATION FORM REDACTED4 Aug 2025View ↗
ATTACHMENT SUMMARY4 Aug 2025View ↗
LOCATION PLAN4 Aug 2025View ↗
EX FIRST FLOOR PLAN4 Aug 2025View ↗
PROP FIRST FLOOR PLAN4 Aug 2025View ↗
EX SECOND FLOOR PLAN4 Aug 2025View ↗
PROP SECOND FLOOR PLAN4 Aug 2025View ↗
View Application Page ↗
Data from the Westminster planning register.
Summary
Reference
25/05461/FULL
Type
Full Planning Permission Application
Applicant
Mr F Simsek
Submitted
4 Aug 2025
Decision date
25 Mar 2026
Decision
Approved
Decision route
Delegated (officer)
How long, really
33
wks · this application
Submission → decision · 25 wks over the 8-week target