Planning Application
25/03302/FULL
59 Nutbourne Street London W10 4HW
Full / Other PlanningQueen's Park ward
Submission
14 May 2025
Target
9 Sep 2025
Decision
29 Sep 2025
Outcome
Approved
Delegated decisionApproved
29 Sep 2025Decided by Jack Morris under delegated powers
Loading map…
Scheme description
Erection of single storey rear extension; Installation of new window and rooflights to outrigger; and Installation of a roof light at main roof level.
Parties
Timeline
14 May 2025
Application submitted
15 Jul 2025
Application validated
29 Sep 2025
Delegated decision: Approved
Supporting documents · 35
1–25 of 35
GRANT OF FULL PP [PE]29 Sep 2025View ↗
DELEGATED REPORT29 Sep 2025View ↗
PROPOSED GROUND FLOOR PLAN15 Sep 2025View ↗
FIRST FLOOR PROPOSED15 Sep 2025View ↗
ATTIC PLAN PROPOSED15 Sep 2025View ↗
ROOF PLAN PROPOSED15 Sep 2025View ↗
SECTIONAL ELEVATION A-A PROPOSED15 Sep 2025View ↗
SECTIONAL ELEVATION B-B PROPOSED15 Sep 2025View ↗
REAR ELEVATION _ PROPOSED15 Sep 2025View ↗
NEIGHBOUR NOTIFICATION LETTER (21D)17 Jul 2025View ↗
SITE NOTICE 21 OR 28 DAYS IF T&C APPL.17 Jul 2025View ↗
ECNSLT-LOCAL AMENITY SOCIETY17 Jul 2025View ↗
ACK-GENERAL LETTER (G/P/C)17 Jul 2025View ↗
INVALID CHASER LETTER (14 DAY RESPONSE)16 Jun 2025View ↗
FLOOD RISK ASSESSMENT10 Jun 2025View ↗
SUSTAINABLE DESIGN STATEMENT10 Jun 2025View ↗
HERITAGE STATEMENT10 Jun 2025View ↗
DESIGN AND ACCESS STATEMENT10 Jun 2025View ↗
RECEIPT OF APPLICATION16 May 2025View ↗
1ST INVALID LETTER16 May 2025View ↗
APPLICATIONFORMREDACTED14 May 2025View ↗
SITE LOCATION PLAN14 May 2025View ↗
DP25.015 - PL _ 01 GROUND FLOOR EXISTING14 May 2025View ↗
DP25.015 - PL _ 02 FIRST FLOOR EXISTING14 May 2025View ↗
DP25.015 - PL _ 03 ROOF PLAN EXISTING14 May 2025View ↗
View Application Page ↗
Data from the Westminster planning register.
Summary
Reference
25/03302/FULL
Ward
Type
Full Planning Permission Application
Applicant
Mr and Mrs Fred and Jo Burstal and Mitton
Submitted
14 May 2025
Decision date
29 Sep 2025
Officer
Council
Decision
Approved
Decision route
Delegated (officer)
How long, really
20
wks · this application
Submission → decision · 12 wks over the 8-week target
Public response
Objections
0
In support
0
Total comments
0