Development Intent
Planning AtlasWestminsterWest EndApplication
Planning Application

24/08979/FULL

Ground Floor 36 Albemarle Street City Of Westminster London W1S 4JE

Full / Other PlanningWest End ward
Submission
20 Dec 2024
Target
4 Mar 2025
Decision
10 Feb 2026
Outcome
Refused
Committee decisionRefused
10 Feb 2026
Determined by the planning committee
Loading map…
Scheme description

Installation of external metal security shutters to the shopfront. (Retrospective application).

Parties
Applicant
Lucas Leong
Officer
Adam Jones
Timeline
20 Dec 2024
Application submitted
7 Jan 2025
Application validated
10 Feb 2026
Committee decision: Refused
Supporting documents · 24
DECISION NOTICE10 Feb 2026View ↗
SUB COMMITTEE REPORT24 Nov 2025View ↗
ECNSLT-INTERNAL CONSULTS6 Oct 2025View ↗
ACK-GENERAL LETTER (G/P/C)15 Jan 2025View ↗
CNSLT-LA SOCIETY15 Jan 2025View ↗
CNSLT-LA SOCIETY15 Jan 2025View ↗
CNSLT-LA SOCIETY15 Jan 2025View ↗
SITE NOTICE 21 OR 28 DAYS IF T&C APPL.15 Jan 2025View ↗
NEIGHBOUR NOTIFICATION LETTER (21D)15 Jan 2025View ↗
RECEIPT OF APPLICATION7 Jan 2025View ↗
1ST INVALID LETTER7 Jan 2025View ↗
FLOOD RISK ASSESSMENT7 Jan 2025View ↗
APPLICATIONFORMREDACTED20 Dec 2024View ↗
FEECALCULATION20 Dec 2024View ↗
ATTACHMENTSUMMARY20 Dec 2024View ↗
LOCATION PLAN20 Dec 2024View ↗
SITELOCATION20 Dec 2024View ↗
SHUTTER-TECHNICAL-SHEET20 Dec 2024View ↗
PLANNING & HERITAGE STATEMENT20 Dec 2024View ↗
PLANNING STATEMENT_INCLUDED_IN_HERITAGE STATEMENT20 Dec 2024View ↗
EXISTING ELEVATIONS20 Dec 2024View ↗
ELEVATION (SIDE) - EXISTING_INCLUDED_IN_ELEVATION (FRONT) - 20 Dec 2024View ↗
PROPOSED ELEVATIONS20 Dec 2024View ↗
ELEVATION (SIDE) - PROPOSED_INCLUDED_IN_ELEVATION (FRONT) - 20 Dec 2024View ↗
View Application Page ↗
Data from the Westminster planning register.
Summary
Reference
24/08979/FULL
Type
Full Planning Permission Application
Applicant
Lucas Leong
Submitted
20 Dec 2024
Decision date
10 Feb 2026
Officer
Decision
Refused
Decision route
Committee
How long, really
60
wks · this application
Submission → decision · 52 wks over the 8-week target
Public response
Objections
0
In support
0
Total comments
1