Planning Application
24/05632/FULL
36 Ordnance Hill London NW8 6PU
Full / Other PlanningRegent's Park ward
Submission
14 Aug 2024
Target
22 Oct 2024
Decision
29 Jan 2025
Outcome
Approved
Delegated decisionApproved
29 Jan 2025Decided by Avani Raven under delegated powers
Loading map…
Scheme description
Excavation of basement under house, extending into the front and rear gardens, and incorporating a front lightwell with stairs and a rear lightwell; loft conversion with dormer extension and replacement rear ground floor extension; installation of air conditioning within enclosure within the rear garden; alterations to the front driveway and entrance; and associated works.
Parties
Timeline
14 Aug 2024
Application submitted
27 Aug 2024
Application validated
29 Jan 2025
Delegated decision: Approved
Supporting documents · 75
1–25 of 75
GRANT OF FULL PP [PE]29 Jan 2025View ↗
DELEGATED REPORT29 Jan 2025View ↗
REVISED DRAWINGS28 Jan 2025View ↗
PROPOSED_12.0 REAR GARDEN IMPACT PLAN3 Dec 2024View ↗
AIA - REV C - NOV 20243 Dec 2024View ↗
AIA - REV C - NOV 20243 Dec 2024View ↗
P07.0A_PROPOSED FRONT ELEVATION15 Oct 2024View ↗
P10.0A_PROPOSED SECTION AA.15 Oct 2024View ↗
P8.0A_PROPOSED REAR ELEVATION15 Oct 2024View ↗
GROUND MOVEMENT ASSESSMENT15 Oct 2024View ↗
DESK STUDY & GROUND REV 115 Oct 2024View ↗
STRUCTURAL METHOD STATEMENT_APPENDIXE_REVA.15 Oct 2024View ↗
STRUCTURAL METHOD STATEMENT_APPENDIXC_REVA.15 Oct 2024View ↗
STRUCTURAL METHODOLOGY STATEMENT9 Oct 2024View ↗
BUILDING CONTROL9 Oct 2024View ↗
STRUCTURAL METHOD STATEMENT8 Oct 2024View ↗
LLFA3 Sep 2024View ↗
NEIGHBOUR NOTIFICATION LETTER (21D)28 Aug 2024View ↗
SITE NOTICE 21 OR 28 DAYS IF T&C APPL.28 Aug 2024View ↗
ACK-GENERAL LETTER (G/P/C)28 Aug 2024View ↗
ECNSLT-INTERNAL CONSULTS28 Aug 2024View ↗
ECNSLT-INTERNAL CONSULTS28 Aug 2024View ↗
ECNSLT-INTERNAL CONSULTS28 Aug 2024View ↗
ECNSLT-INTERNAL CONSULTS28 Aug 2024View ↗
ECNSLT-INTERNAL CONSULTS28 Aug 2024View ↗
View Application Page ↗
Data from the Westminster planning register.
Summary
Reference
24/05632/FULL
Ward
Type
Full Planning Permission Application
Applicant
Ms Edwige Radigois
Submitted
14 Aug 2024
Decision date
29 Jan 2025
Officer
Council
Decision
Approved
Decision route
Delegated (officer)
How long, really
24
wks · this application
Submission → decision · 16 wks over the 8-week target
Public response
Objections
0
In support
0
Total comments
1