Planning Application
24/03039/FULL
16 Beaumont Mews London W1G 6EJ
Full / Other PlanningMarylebone ward
Submission
8 May 2024
Target
3 Jul 2024
Decision
19 Feb 2025
Outcome
Approved
Committee decisionApproved
19 Feb 2025Determined by the planning committee
Loading map…
Scheme description
Excavation of single storey basement and the demolition and replacement of the mews building with an additional mansard storey to provide additional residential floorspace including the installation of an air source heat pump at roof level (Class C3).
Parties
Timeline
8 May 2024
Application submitted
19 Feb 2025
Committee decision: Approved
Supporting documents · 37
1–25 of 37
DELEGATED REPORT19 Feb 2026View ↗
GRANT OF FULL PP [PE]19 Feb 2025View ↗
SUB COMMITTEE REPORT18 Feb 2025View ↗
REVISED DESIGN AND ACCESS STATEMENT17 Jan 2025View ↗
EXISTING AND PROPOSED FRONT AND REAR ELEVATIONS23 Oct 2024View ↗
EXISTING AND PROPOSED FLOOR PLANS23 Oct 2024View ↗
DEMOLITION DRAWINGS23 Oct 2024View ↗
EXISTING AND PROPOSED SECTCTIONS23 Oct 2024View ↗
EXISTING AND PROPOSED SIDE ELEVATIONS23 Oct 2024View ↗
PROPOSED SOUTH ELEVATION23 Oct 2024View ↗
PROPOSED SOUTH ELEVATION23 Oct 2024View ↗
FRONT ELEVATION DETAILS GROUND FLOOR23 Oct 2024View ↗
SITE PLAN23 Oct 2024View ↗
LOCATION PLAN2 Sep 2024View ↗
OBJECTION11 Jun 2024View ↗
ACK-GENERAL LETTER (G/P/C)16 May 2024View ↗
CNSLT-LA SOCIETY16 May 2024View ↗
ECNSLT-INTERNAL CONSULTS16 May 2024View ↗
ECNSLT-INTERNAL CONSULTS16 May 2024View ↗
SITE NOTICE 21 OR 28 DAYS IF T&C APPL.16 May 2024View ↗
NEIGHBOUR NOTIFICATION LETTER (21D)16 May 2024View ↗
RECEIPT OF APPLICATION13 May 2024View ↗
APPLICATIONFORMREDACTED8 May 2024View ↗
LOCATION PLAN8 May 2024View ↗
DEMOLITION DRAWINGS8 May 2024View ↗
View Application Page ↗
Data from the Westminster planning register.
Summary
Reference
24/03039/FULL
Ward
Type
Full Planning Permission Application
Applicant
Mr Miles Berry
Submitted
8 May 2024
Decision date
19 Feb 2025
Officer
Council
Decision
Approved
Decision route
Committee
How long, really
41
wks · this application
Submission → decision · 33 wks over the 8-week target
Public response
Objections
5
In support
0
Total comments
6