23 Nov 2023
Target
23 Feb 2024
Decision
22 Aug 2024
Outcome
Refused
Delegated decisionRefused
22 Aug 2024Decided by Richard Langston under delegated powers
Loading map…
Scheme description
Installation of a extract ducting within the lightwell at basement level, in association with the installation of internal air conditioning unit at the Crescent Hotel within the basement level. (Retrospective Application, Linked with 23/08147/LBC)
Parties
Timeline
23 Nov 2023
Application submitted
29 Dec 2023
Application validated
22 Aug 2024
Delegated decision: Refused
Supporting documents · 25
REFUSAL-FULL PP [PE]22 Aug 2024View ↗
DELEGATED REPORT22 Aug 2024View ↗
ENVIRONMENTAL HEALTH24 Apr 2024View ↗
NEIGHBOUR NOTIFICATION LETTER (21D)9 Jan 2024View ↗
SITE NOTICE 21 OR 28 DAYS IF T&C APPL.9 Jan 2024View ↗
ECNSLT-INTERNAL CONSULTS9 Jan 2024View ↗
CNSLT-LA SOCIETY9 Jan 2024View ↗
ACK-GENERAL LETTER (G/P/C)9 Jan 2024View ↗
HERITAGE STATEMENT29 Dec 2023View ↗
FLOOD RISK ASSESSMENT29 Dec 2023View ↗
SUSTAINABLE DESIGN STATEMENT29 Dec 2023View ↗
EXITING ELEVATION PLANS29 Dec 2023View ↗
PRIOR BASEMENT PLANS29 Dec 2023View ↗
RECEIPT OF APPLICATION4 Dec 2023View ↗
RECEIPT OF APPLICATION4 Dec 2023View ↗
1ST INVALID LETTER4 Dec 2023View ↗
APPLICATIONFORMREDACTED23 Nov 2023View ↗
ATTACHMENTSUMMARY23 Nov 2023View ↗
LOCATION PLAN23 Nov 2023View ↗
ACOUSTIC REPORT23 Nov 2023View ↗
SITE & GROUND FLOOR PLAN23 Nov 2023View ↗
PROPOSED AC UNIT23 Nov 2023View ↗
PROPSOED ELEVATION PLANS23 Nov 2023View ↗
DESIGN & ACCESS STATEMENT23 Nov 2023View ↗
PHOTO SCHEDULE23 Nov 2023View ↗
View Application Page ↗
Data from the Westminster planning register.
Summary
Reference
23/08146/FULL
Ward
Type
Full Planning Permission Application
Applicant
mr Nirvait Dhillon
Submitted
23 Nov 2023
Decision date
22 Aug 2024
Officer
Council
Decision
Refused
Decision route
Delegated (officer)
How long, really
39
wks · this application
Submission → decision · 31 wks over the 8-week target
Public response
Objections
0
In support
0
Total comments
0