Development Intent
Planning AtlasWestminsterSt James'sApplication
Planning Application

23/06521/FULL

39 - 40 Bedford Street London WC2E 9ER

Full / Other PlanningSt James's ward
Submission
21 Sep 2023
Target
16 Nov 2023
Decision
26 Apr 2024
Outcome
Withdrawn
Delegated decisionWithdrawn
26 Apr 2024
Decided by Zulekha Hosenally under delegated powers
Loading map…
Scheme description

Installation of new duct shaft and mechanical plant to rear of building; lowering of ground floor window cillls on Bedford Street and Maiden Lane elevations; opening up of existing blocked up windows and replacement doors on Maiden Lane; new stone steps; new fa�ade lighting to ground floor elevations and regrading of pavement to create level access from Bedford Street.

Parties
Applicant
Shaftesbury Capital PLC
Timeline
21 Sep 2023
Application submitted
26 Apr 2024
Delegated decision: Withdrawn
Supporting documents · 42
125 of 42
SUB COMMITTEE REPORT30 Apr 2024View ↗
NORTHBANK BID - REDACTED27 Feb 2024View ↗
EXISTING AND PROPOSED SECTIONS STALL RISER15 Jan 2024View ↗
CGL-Z1-00-GA-A-SK200 REV. 0115 Jan 2024View ↗
ECNSLT-INTERNAL CONSULTS30 Nov 2023View ↗
ECNSLT-INTERNAL CONSULTS30 Nov 2023View ↗
RECEIPT OF APPLICATION27 Sep 2023View ↗
ACK-GENERAL LETTER (G/P/C)27 Sep 2023View ↗
NEIGHBOUR NOTIFICATION LETTER (21D)27 Sep 2023View ↗
SITE NOTICE 21 OR 28 DAYS IF T&C APPL.27 Sep 2023View ↗
ECNSLT-INTERNAL CONSULTS27 Sep 2023View ↗
CNSLT-LA SOCIETY27 Sep 2023View ↗
CNSLT-LA SOCIETY27 Sep 2023View ↗
APPLICATIONFORMREDACTED21 Sep 2023View ↗
FEECALCULATION21 Sep 2023View ↗
ATTACHMENTSUMMARY21 Sep 2023View ↗
HERITAGE STATEMENT21 Sep 2023View ↗
OPERATIONAL MANAGEMENT STATEMENT21 Sep 2023View ↗
PLANNING NOISE ASSESSMENT21 Sep 2023View ↗
STATEMENT OF COMMUNITY INVOLVEMENT21 Sep 2023View ↗
SUSTAINABILITY STATEMENT21 Sep 2023View ↗
FIRE STATEMENT ? REV 121 Sep 2023View ↗
-EXISTING FIRST FLOOR PLAN21 Sep 2023View ↗
-PROPOSED FIRST FLOOR PLAN21 Sep 2023View ↗
-EXISTING BASEMENT PLAN21 Sep 2023View ↗
View Application Page ↗
Data from the Westminster planning register.
Summary
Reference
23/06521/FULL
Type
Full Planning Permission Application
Applicant
Shaftesbury Capital PLC
Submitted
21 Sep 2023
Decision date
26 Apr 2024
Decision
Withdrawn
Decision route
How long, really
31
wks · this application
Submission → decision · 23 wks over the 8-week target
Public response
Objections
1
In support
0
Total comments
1