Development Intent
Planning AtlasWestminsterVincent SquareApplication
Planning Application

22/08691/FULL

32 Maunsel Street London SW1P 2QN

Full / Other PlanningVincent Square ward
Submission
23 Dec 2022
Target
3 Mar 2023
Decision
5 Apr 2023
Outcome
Approved
Committee decisionApproved
5 Apr 2023
Determined by the planning committee
Loading map…
Scheme description

Erection of single storey rear extension at first floor.

Parties
Applicant
Rachael Robathan
Timeline
23 Dec 2022
Application submitted
6 Jan 2023
Application validated
5 Apr 2023
Committee decision: Approved
Supporting documents · 36
125 of 36
GRANT OF FULL PP [PE]5 Apr 2023View ↗
SUB COMMITTEE REPORT4 Apr 2023View ↗
PLANNING COMMITEE MINUTES4 Apr 2023View ↗
NEIGHBOUR NOTIFICATION LETTER (21D)11 Jan 2023View ↗
ACK-GENERAL LETTER (G/P/C)10 Jan 2023View ↗
CNSLT-LA SOCIETY10 Jan 2023View ↗
CNSLT-LA SOCIETY10 Jan 2023View ↗
SITE NOTICE 21 OR 28 DAYS IF T&C APPL.10 Jan 2023View ↗
NEIGHBOUR NOTIFICATION LETTER (21D)10 Jan 2023View ↗
FLOOD RISK ASSESSMENT6 Jan 2023View ↗
RECEIPT OF APPLICATION30 Dec 2022View ↗
1ST INVALID LETTER30 Dec 2022View ↗
APPLICATIONFORMREDACTED23 Dec 2022View ↗
FEECALCULATION23 Dec 2022View ↗
ATTACHMENTSUMMARY23 Dec 2022View ↗
LOCATION PLAN23 Dec 2022View ↗
DESIGN AND ACCESS23 Dec 2022View ↗
SUSTAINABILITY STATEMENT23 Dec 2022View ↗
EXISTING GORUND FLOOR PLAN23 Dec 2022View ↗
EXISTING FIRST FLOOR PLAN23 Dec 2022View ↗
EXISTING SECOND FLOOR PLAN23 Dec 2022View ↗
EXISTING ROOF23 Dec 2022View ↗
EXISTING REAR ELEVATION23 Dec 2022View ↗
EXISTING SSECTION AA23 Dec 2022View ↗
EXISTING SECTION BB23 Dec 2022View ↗
View Application Page ↗
Data from the Westminster planning register.
Summary
Reference
22/08691/FULL
Type
Full Planning Permission Application
Applicant
Rachael Robathan
Submitted
23 Dec 2022
Decision date
5 Apr 2023
Decision
Approved
Decision route
Committee
How long, really
15
wks · this application
Submission → decision · 7 wks over the 8-week target