Planning Application

21/05157/FULL

Electrical Sub Station Leicester Square London WC2H 0QQ

Full / Other PlanningSt James's ward
Submission
27 Jul 2021
Target
21 Sep 2021
Decision
6 Sep 2021
Outcome
Approved
Delegated decisionApproved
6 Sep 2021
Decided by Phoebe Graham under delegated powers
Loading map…
Scheme description

Construction of an upstand and steps for water mains flood protection works to the subterranean electricity substation at Leicester Square.

Parties
Applicant
LONDON POWER NETWORKS PLC
Timeline
27 Jul 2021
Application submitted
6 Sep 2021
Delegated decision: Approved
Supporting documents · 23
GRANT OF FULL PP [PE]6 Sep 2021View ↗
DELEGATED REPORT6 Sep 2021View ↗
RECEIPT OF APPLICATION3 Aug 2021View ↗
ACK-GENERAL LETTER (G/P/C)3 Aug 2021View ↗
CNSLT-LA SOCIETY3 Aug 2021View ↗
ECNSLT-INTERNAL CONSULTS3 Aug 2021View ↗
ECNSLT-INTERNAL CONSULTS3 Aug 2021View ↗
SITE NOTICE 21 OR 28 DAYS IF T&C APPL.3 Aug 2021View ↗
NEIGHBOUR NOTIFICATION LETTER (21D)3 Aug 2021View ↗
LOCATION PLAN(1)27 Jul 2021View ↗
SITE PLAN(1)27 Jul 2021View ↗
VIEWPOINTS MAP(1)27 Jul 2021View ↗
PROPOSED PLAN(3)27 Jul 2021View ↗
EXISTING AND PROPOSED SECTION A-A AND B-B(4)27 Jul 2021View ↗
PHOTOGRAPHIC PLATES A-E27 Jul 2021View ↗
CONSTRUCTION HOARDING OVER THE LEICESTER SQUARE SUBSTATION -27 Jul 2021View ↗
VISUALISATION EXISTING AND PROPOSED27 Jul 2021View ↗
NOTICE TO OWNERS JULY 2127 Jul 2021View ↗
WCC CVR 27JULY2127 Jul 2021View ↗
PLANNING DESIGN AND ACCESS STATEMENT27 Jul 2021View ↗
DETAILED DESIGN REPORT - LPN SUBSTATION WATER MAIN FLOOD PRO27 Jul 2021View ↗
ATTACHMENTSUMMARY27 Jul 2021View ↗
APPLICATIONFORMREDACTED27 Jul 2021View ↗
View Application Page ↗
Data from the Westminster planning register.
Summary
Reference
21/05157/FULL
Type
Full Planning Permission Application
Applicant
LONDON POWER NETWORKS PLC
Submitted
27 Jul 2021
Decision date
6 Sep 2021
Decision
Approved
Decision route
Delegated (officer)
How long, really
6
wks · this application
Submission → decision
Public response
Objections
0
In support
0
Total comments
0