Planning Application

20/07275/FULL

403 Harrow Road London W9 3NF

Full / Other PlanningHarrow Road ward
Submission
13 Nov 2020
Target
16 Apr 2021
Decision
25 Aug 2021
Outcome
Refused
Delegated decisionRefused
25 Aug 2021
Decided by Frederica Cooney under delegated powers
Loading map…
Scheme description

Erection of an extension at the rear of the property at ground and first floor levels to provide additional office accommodation at ground floor and the creation of a 1 bedroom residential unit (Class C3) at first floor level.

Why it was refused
Reason 1

Because of its depth, width,overall massing and design the the proposed extensions would harm the appearance of this building and this part of the City. This would not meet Policy 38 and 40 of the City Plan 2019 - 2040 (April 2021). (X16BC)

Policies cited
City Plan 38
City Plan 40
Parties
Applicant
Mr Chowdhury
Timeline
13 Nov 2020
Application submitted
19 Feb 2021
Application validated
25 Aug 2021
Delegated decision: Refused
Supporting documents · 20
DELEGATED REPORT25 Aug 2021View ↗
REFUSAL-FULL PP [PE]25 Aug 2021View ↗
ACK-GENERAL LETTER (G/P/C)22 Feb 2021View ↗
CNSLT-LA SOCIETY22 Feb 2021View ↗
CNSLT-LA SOCIETY22 Feb 2021View ↗
SITE NOTICE 21 OR 28 DAYS IF T&C APPL.22 Feb 2021View ↗
NEIGHBOUR NOTIFICATION LETTER (21D)22 Feb 2021View ↗
EXISTING DRAWINGS19 Feb 2021View ↗
PROPOSED DRAWINGS19 Feb 2021View ↗
2ND INVALID LETTER10 Dec 2020View ↗
RECEIPT OF APPLICATION18 Nov 2020View ↗
1ST INVALID LETTER18 Nov 2020View ↗
LOCATION PLAN13 Nov 2020View ↗
EXISTING FIRST FLOOR13 Nov 2020View ↗
EXISTING REAR ELEVATION13 Nov 2020View ↗
EXISTING SIDE ELEVATION13 Nov 2020View ↗
EXISTING SIDE ELEVATION13 Nov 2020View ↗
EXISTING GROUND FLOOR13 Nov 2020View ↗
ATTACHMENTSUMMARY13 Nov 2020View ↗
APPLICATIONFORMREDACTED13 Nov 2020View ↗
View Application Page ↗
Data from the Westminster planning register.
Summary
Reference
20/07275/FULL
Type
Full Planning Permission Application
Applicant
Mr Chowdhury
Submitted
13 Nov 2020
Decision date
25 Aug 2021
Decision
Refused
Decision route
Delegated (officer)
How long, really
41
wks · this application
Submission → decision · 33 wks over the 8-week target
Public response
Objections
5
In support
0
Total comments
5