Planning Application
20/05463/LBC
4 Queen Anne Street London W1G 9LQ
Listed BuildingMarylebone ward
Submission
28 Aug 2020
Target
23 Oct 2020
Decision
14 May 2025
Outcome
No determination
Committee decisionNo determination
14 May 2025Determined by the planning committee
Loading map…
Scheme description
Removal of existing air conditions units, installation of replacement air conditioning unit within acoustic enclosure and replacement of window panels. (Linked to 20/05462/FULL)
Parties
Timeline
28 Aug 2020
Application submitted
14 May 2025
Committee decision: No determination
Supporting documents · 27
1–25 of 27
FINALLY DISPOSED OF NOTIFICATION LETTER29 Apr 2025View ↗
ADDITIONAL ACOUSTIC REPORT4 Nov 2023View ↗
PROPOSED SECTION4 Nov 2023View ↗
PROPOSED REAR ELEVATION4 Nov 2023View ↗
SUB COMMITTEE REPORT21 Feb 2023View ↗
ACK-GENERAL LETTER (G/P/C)10 Sep 2020View ↗
RECEIPT OF APPLICATION8 Sep 2020View ↗
SITE LOCATION PLAN28 Aug 2020View ↗
SU002 EXISTING BLOCK PLAN28 Aug 2020View ↗
SU03 EXISTING LOWER GROUND FLOOR PLAN28 Aug 2020View ↗
SU04 EXISTING GROUND FLOOR PLAN28 Aug 2020View ↗
SU05 EXISTING SECTION A-A28 Aug 2020View ↗
SU06 EXISTING REAR ELEVATION28 Aug 2020View ↗
PL001 PROPOSED BLOCK PLAN28 Aug 2020View ↗
PL02 PROPOSED LOWER GROUND FLOOR PLAN-MODEL-00028 Aug 2020View ↗
PL03 PROPOSED GROUND FLOOR PLAN-MODEL-00028 Aug 2020View ↗
PL04 PROPOSED SECTION28 Aug 2020View ↗
PL05 PROPOSED REAR ELEVATION-MODEL-00028 Aug 2020View ↗
PL006 PROPOSED ENCLOSURE DETAIL28 Aug 2020View ↗
PLANT NOISE IMPACT REPORT28 Aug 2020View ↗
PUMY-P_PRODUCT_INFORMATION_SHEET_2018_128 Aug 2020View ↗
PLANNING HERITAGE DESIGN AND ACCESS STATEMENT DOCUMENTS28 Aug 2020View ↗
PLANNING HERITAGE DESIGN AND ACCESS STATEMENT28 Aug 2020View ↗
HERITAGESTATEMENT_INCLUDED_IN_PLANNINGSTATEMENT28 Aug 2020View ↗
DESIGNANDACCESSSTATEMENT_INCLUDED_IN_PLANNINGSTATEMENT28 Aug 2020View ↗
View Application Page ↗
Data from the Westminster planning register.
Summary
Reference
20/05463/LBC
Ward
Type
Listed Building Consent Application
Applicant
Dr Neville Bass
Submitted
28 Aug 2020
Decision date
14 May 2025
Officer
Council
Decision
No determination
Decision route
Committee
How long, really
246
wks · this application
Submission → decision · 238 wks over the 8-week target
Public response
Objections
4
In support
0
Total comments
4