Development Intent
Planning AtlasSouthwarkSt GilesApplication
Planning Application

26/AP/0389

Camberwell Leisure Centre Artichoke Place London Southwark SE5 8TS

Listed BuildingSt Giles ward
Submission
9 Feb 2026
Target
6 Apr 2026
Decision
27 Apr 2026
Outcome
Approved
Committee decisionApproved
27 Apr 2026
Determined by the planning committee
Loading map…
Scheme description

Listed building consent for Installation of air source heat pumps (ASHPs), a new electric substation, and relocation of bin storage areas and cycle parking to accommodate an ASHP enclosure in the area adjacent the centre entrance. Remedial / replacement works to existing windows and doors are to take place as well as the installation of thermal insulation in the roof zone above the pool halls. Photovoltaic panels proposed over pool and gym hall pitched roofs.

Parties
Applicant
Ms Tamara Kahn
Timeline
9 Feb 2026
Application submitted
10 Feb 2026
Application validated
27 Apr 2026
Committee decision: Approved
Supporting documents · 30
125 of 30
DECISION NOTICE - LBC - GRANT27 Apr 2026View ↗
OFFICER ASSESSMENT27 Apr 2026View ↗
SIGNED EOT20 Apr 2026View ↗
DECARBONISATION ADDENDUM20 Apr 2026View ↗
SPD-ART-CL-XX-DR-A-10103-GA REV 0520 Apr 2026View ↗
SPD-ART-CL-XX-DR-A-10100-GA REV 0520 Apr 2026View ↗
SPD-ART-CL-XX-DR-A-10000-GA REV 0920 Apr 2026View ↗
TIME EXTENSION LETTER15 Apr 2026View ↗
TIME EXTENSION LETTER25 Mar 2026View ↗
HISTORIC ENGLAND19 Feb 2026View ↗
PRESS NOTICE - 19/02/202617 Feb 2026View ↗
VALID APPLICATION LETTER WITH INVOICE12 Feb 2026View ↗
FILE COPY - NEIGHBOUR NOTIFICATION+LIST12 Feb 2026View ↗
APPLICATION FORM - WITHOUT PERSONAL DATA9 Feb 2026View ↗
NOISE IMPACT ASSESSMENT9 Feb 2026View ↗
SITE LOCATION PLAN9 Feb 2026View ↗
SPD-A-RT-CL-XX-DR-A-000019 Feb 2026View ↗
SPD--ART-CL-XX-DR-A-10003 REV P019 Feb 2026View ↗
SPD-ART-CL-XX-DR-A-10015 REV P039 Feb 2026View ↗
SPD-ART-CL-XX-DR-A-10016 REV P029 Feb 2026View ↗
SPD--ART-CL-XX-DR-A-10101 REV P049 Feb 2026View ↗
SPD-ART-CL-XX-DR-A-10102 REV P049 Feb 2026View ↗
SPD--ART-CL-XX-DR-A-10104 REV P029 Feb 2026View ↗
SPD-ART-DL-XX-DR-A-10106 REV P019 Feb 2026View ↗
SPD-GED-CL-B1-D-M-00003 REV P029 Feb 2026View ↗
View Application Page ↗
Data from the Southwark planning register.
Summary
Reference
26/AP/0389
Type
Listed Building Consent
Applicant
Ms Tamara Kahn
Submitted
9 Feb 2026
Decision date
27 Apr 2026
Council
Decision
Approved
Decision route
Committee
How long, really
11
wks · this application
Submission → decision · 3 wks over the 8-week target
Public response
Objections
0
In support
0
Total comments
0