Planning Application
22/AP/0424
171-175 Peckham High Street London Southwark SE15 5SL
Full / Other PlanningPeckham ward
Submission
14 Feb 2022
Target
26 May 2022
Decision
9 Sep 2022
Outcome
Approved
Committee decisionApproved
9 Sep 2022Determined by the planning committee
Loading map…
Scheme description
Retention of use of the property as a large HMO (sui generis use class) from previous use as a hostel (sui generis use class) to accommodate 27 people in 18 households.
Parties
Timeline
14 Feb 2022
Application submitted
1 Apr 2022
Application validated
9 Sep 2022
Committee decision: Approved
Supporting documents · 27
1–25 of 27
TIME EXTENSION LETTER12 Sep 2022View ↗
DECISION NOTICE - MINOR - GRANT9 Sep 2022View ↗
OFFICER ASSESSMENT9 Sep 2022View ↗
TIME EXTENSION LETTER30 Aug 2022View ↗
SITE LOCATION PLAN UPDATED23 May 2022View ↗
FILE COPY - NEIGHBOUR NOTIFICATION+LIST12 Apr 2022View ↗
VALID APPLICATION LETTER WITH INVOICE4 Apr 2022View ↗
REASONABLE EXCEPTION STATEMENT1 Apr 2022View ↗
Planning statement1 Apr 2022View ↗
EMERGENCY TEST CERTIFICATE FOR LIGHTS1 Apr 2022View ↗
GAS CERT1 Apr 2022View ↗
GAS CERT NO 21 Apr 2022View ↗
PAT CERTIFICATE1 Apr 2022View ↗
PAT TESTING SCHEDULE1 Apr 2022View ↗
ELECTRICAL INSTALATION REPORT1 Apr 2022View ↗
FIRE RISK ASSESMENT1 Apr 2022View ↗
HMO LICENSE1 Apr 2022View ↗
PLANNING STATEMENT1 Apr 2022View ↗
CROWN MANSIONS REASONABLE EXCEPTION STATEMENT1 Apr 2022View ↗
CROWN MANSIONS ELECTRICAL INSTALATION REPORT1 Apr 2022View ↗
CROWN MANSIONS EMERGENCY LIGHT TEST CERTIFICATE1 Apr 2022View ↗
FIRE ALARM MAINTENANCE REPORT1 Apr 2022View ↗
FIRE RISK ASSESMENT1 Apr 2022View ↗
PAT CERTIFICATE CROWN MANSIONS1 Apr 2022View ↗
PAT TESTING SCHEDULE 2021 CROWN MANSIONS1 Apr 2022View ↗
View Application Page ↗
Data from the Southwark planning register.
Summary
Reference
22/AP/0424
Ward
Type
Minor application
Applicant
Mr Oral Alan
Submitted
14 Feb 2022
Decision date
9 Sep 2022
Officer
Council
Decision
Approved
Decision route
Committee
How long, really
30
wks · this application
Submission → decision · 22 wks over the 8-week target
Public response
Objections
0
In support
0
Total comments
0