Planning Application
20/AP/2421
Hilton London Bankside 2-8 Great Suffolk Street London Southwark SE1 0UG
Full / Other PlanningBorough & Bankside ward
Submission
25 Aug 2020
Target
26 Nov 2020
Decision
24 Feb 2022
Outcome
Approved
Committee decisionApproved
24 Feb 2022Determined by the planning committee
Loading map…
Scheme description
Proposed infill extension of existing hotel at 4th, 5th and 6th floor, with proposed single storey rooftop extension to provide additional hotel bedrooms, with associated plant, cycle parking and ancillary works
Parties
Timeline
25 Aug 2020
Application submitted
27 Aug 2020
Application validated
24 Feb 2022
Committee decision: Approved
Supporting documents · 101
1–25 of 101
Section 106 - Legal Agreements2 Mar 2022View ↗
DECISION NOTICE - MAJOR - GRANT24 Feb 2022View ↗
TIME EXTENSION LETTER21 Feb 2022View ↗
TIME EXTENSION LETTER10 Feb 2022View ↗
TIME EXTENSION LETTER6 Jan 2022View ↗
TIME EXTENSION LETTER9 Dec 2021View ↗
COMMITTEE REPORT - ITEM 6.211 Oct 2021View ↗
TIME EXTENSION LETTER22 Sep 2021View ↗
6739 K0910 Jun 2021View ↗
DAYLIGHT/SUNLIGHT CUMULATIVE ADDENDUM1 Jun 2021View ↗
ENERGY STATEMENT REV C1 Jun 2021View ↗
REVISED COVER LETTER10 May 2021View ↗
ADDENDUM TO DESIGN & ACCESS STATEMENT10 May 2021View ↗
ACCOMMODATION SCHEDULE10 May 2021View ↗
AREA SCHEDULE10 May 2021View ↗
GUESTROOM SCHEDULE10 May 2021View ↗
(PL) 022 REV B10 May 2021View ↗
(PL) 023 REV B10 May 2021View ↗
(PL) 030 REV B10 May 2021View ↗
(PL) 031 REV B10 May 2021View ↗
(PL) 032 REV B10 May 2021View ↗
(PL) 037 REV A10 May 2021View ↗
ENVIRONMENTAL NOISE ASSESSMENT REV 0410 May 2021View ↗
VENTILATION/EXTRACTION STATEMENT10 May 2021View ↗
AIR QUALITY ASSESSMENT REV 0310 May 2021View ↗
View Application Page ↗
Data from the Southwark planning register.
Summary
Reference
20/AP/2421
Type
Major application
Applicant
Not disclosed
Submitted
25 Aug 2020
Decision date
24 Feb 2022
Officer
Council
Decision
Approved
Decision route
Committee
How long, really
78
wks · this application
Submission → decision · 70 wks over the 8-week target
Public response
Objections
9
In support
0
Total comments
9