Development Intent
Planning AtlasRichmond Upon ThamesHam, Petersham & Richmond Riverside Ward [HMP]Application
Planning Application

PA25/4017

The Manor House, River Lane, Petersham, Richmond, TW10 7AG

HouseholderHam, Petersham & Richmond Riverside Ward [HMP] wardListed Buildings: Listed Building Grade II
Submission
6 Nov 2025
Target
1 Jan 2026
Decision
19 Mar 2026
Outcome
Approved
Delegated decisionApproved
19 Mar 2026
Decided by Phil Shipton under delegated powers
Loading map…
Scheme description

Internal refurbishment of the main house with minor modifications along with a

Timeline
6 Nov 2025
Application submitted
19 Mar 2026
Delegated decision: Approved
Supporting documents · 89
125 of 89
Application Form - Without Personal Data6 Nov 2025View ↗
The location plan6 Nov 2025View ↗
EXISTING SITE PLAN6 Nov 2025View ↗
EXISTING BASEMENT FLOOR PLAN6 Nov 2025View ↗
EXISTING GROUND FLOOR PLAN6 Nov 2025View ↗
EXISTING FIRST FLOOR PLAN6 Nov 2025View ↗
EXISTING SECOND FLOOR PLAN6 Nov 2025View ↗
EXISTING ROOF PLAN6 Nov 2025View ↗
EXISTING NORTH ELEVATION 16 Nov 2025View ↗
EXISTING EAST ELEVATION 16 Nov 2025View ↗
EXISTING SOUTH ELEVATION 16 Nov 2025View ↗
EXISTING WEST ELEVATION 16 Nov 2025View ↗
EXISTING NORTH ELEVATION 26 Nov 2025View ↗
EXISTING EAST ELEVATION 26 Nov 2025View ↗
EXISTING SOUTH ELEVATION 26 Nov 2025View ↗
EXISTING WEST ELEVATION 26 Nov 2025View ↗
DEMOLITION BASEMENT FLOOR PLAN6 Nov 2025View ↗
DEMOLITION GROUND FLOOR PLAN 16 Nov 2025View ↗
DEMOLITION GROUND FLOOR PLAN 26 Nov 2025View ↗
DEMOLITION FIRST FLOOR PLAN6 Nov 2025View ↗
DEMOLITION SECOND FLOOR PLAN6 Nov 2025View ↗
PROPOSED GF DRAINAGE STRATEGY6 Nov 2025View ↗
PROPOSED 1F DRAINAGE STRATEGY6 Nov 2025View ↗
PROPOSED 2F DRAINAGE STRATEGY6 Nov 2025View ↗
PROPOSED SITE PLAN6 Nov 2025View ↗
View Application Page ↗
Data from the Richmond Upon Thames planning register.
Summary
Reference
PA25/4017
Type
Householder Application
Applicant
Submitted
6 Nov 2025
Decision date
19 Mar 2026
Decision
Approved
Decision route
How long, really
19
wks · this application
Submission → decision · 11 wks over the 8-week target