Planning Application
25/P3731
263 London Road, Mitcham, Merton
Full / Other PlanningFigges Marsh ward
Submission
12 Dec 2025
Target
6 Feb 2026
Decision
24 Feb 2026
Outcome
Approved
Delegated decisionApproved
24 Feb 2026Decided by Lan Pham under delegated powers
Loading map…
Scheme description
EXTERNAL ALTERATIONS COMPRISING NEW EXTERNAL WALL INSULATION WITH RENDER AND BRICKSLIP FINISH, NEW WINDOWS AND DOORS, NEW INSULATED ROOF SYSTEM AND PROVISION OF MVHR TO PROVIDE IMPROVED THERMAL PERFORMANCE.
Parties
Timeline
12 Dec 2025
Application submitted
24 Feb 2026
Delegated decision: Approved
Supporting documents · 52
1–25 of 52
Proposed First Floor Plan.pdfView ↗
Proposed South-East Material Strategy Elevation.pdfView ↗
Fourth Floor Demolition Plan.pdfView ↗
Proposed Roof Plan.pdfView ↗
CIL Form 1.pdfView ↗
Construction Phase Plan.pdfView ↗
Design and Access Statement Part 1 of 5.pdfView ↗
Design and Access Statement Part 2 of 5.pdfView ↗
Design and Access Statement Part 3 of 5.pdfView ↗
Existing Fifth Floor Plan.pdfView ↗
Existing Fourth Floor Plan.pdfView ↗
Existing Ground Floor Plan.pdfView ↗
Existing North-East Elevation.pdfView ↗
Existing North-West Elevation.pdfView ↗
Existing Roof Plan.pdfView ↗
Existing Second Floor Plan.pdfView ↗
Existing Section A.pdfView ↗
Existing Section B.pdfView ↗
Existing South-East Elevation.pdfView ↗
Existing South-West Elevation.pdfView ↗
Existing Third Floor Plan.pdfView ↗
Fifth Floor Demolition Plan.pdfView ↗
First Floor Demolition Plan.pdfView ↗
Ground Floor Demolition Plan.pdfView ↗
LocationPlan.pdfView ↗
View Application Page ↗
Data from the Merton planning register.
Summary
Reference
25/P3731
Ward
Type
Full Planning Permission
Applicant
Clarion Housing Group
Submitted
12 Dec 2025
Decision date
24 Feb 2026
Officer
Council
Decision
Approved
Decision route
Delegated (officer)
How long, really
11
wks · this application
Submission → decision · 3 wks over the 8-week target