25/03387/NMC

Hampton House 20 Albert Embankment London SE1 7TJ

Non-Material AmendmentVauxhall wardVauxhall Opportunity Area
Submission
29 Oct 2025
Target
26 Nov 2025
Decision
20 Jan 2026
Outcome
Approved
Delegated decisionApproved
20 Jan 2026
Decided by Nathan Barrett under delegated powers
Loading map…
Scheme description

Application for a non-material amendment following a grant of planning permission ref: 14/03600/VOC (Variation of condition 2 (approved plans) of planning permission ref:- 13/03582/VOC (Demolition and redevelopment of the existing building and the erection of a part 15, part 16-24, part 19-27 storey building to provide a residential led mixed use development comprising ground floor cafe/restaurant uses (A3); office (B1); residents gym and members lounge; and 252 residential units, together with ancillary residential facilities, associated amenity space, car, motorcycle and cycle parking, access and servicing, refuse storage and collection facilities and landscaped public piazza) Amendment so

Parties
Applicant
St James Group
Timeline
29 Oct 2025
Application submitted
20 Jan 2026
Delegated decision: Approved
Supporting documents · 11
Delegated Register20 Jan 2026View ↗
COVERING LETTER29 Oct 2025View ↗
PROPOSED GROUND FLOOR SITE PLAN29 Oct 2025View ↗
PROPOSED PLANT UNITS PLAN, ELEVATION AND SECTION29 Oct 2025View ↗
PROPOSED CYCLE RACKS PLANS, ELEVATIONS AND SECTION29 Oct 2025View ↗
GROUND FLOOR PLAN29 Oct 2025View ↗
PROPOSED FIRST FLOOR PLAN29 Oct 2025View ↗
GENERAL ARRANGEMENT FIRST FLOOR PLAN29 Oct 2025View ↗
APPLICATION FORM - WITHOUT PERSONAL DATA29 Oct 2025View ↗
NOISE IMPACT ASSESSMENT29 Oct 2025View ↗
THE LOCATION PLAN29 Oct 2025View ↗
View Application Page ↗
Data from the Lambeth planning register.
Summary
Reference
25/03387/NMC
Type
Non Material Change - Minor Amendment
Applicant
St James Group
Submitted
29 Oct 2025
Decision date
20 Jan 2026
Council
Decision
Approved
Decision route
Delegated (officer)
How long, really
12
wks · this application
Submission → decision · 4 wks over the 8-week target
Public response
Objections
0
In support
0
Total comments
0