Planning Application
22/00342/LB
The South Bank Centre Belvedere Road London SE1
Listed BuildingBishops wardConservation Area: CA38 : South Bank Conservation Area
Submission
26 Jan 2022
Target
14 Apr 2022
Decision
14 Apr 2022
Outcome
Approved
Committee decisionApproved
14 Apr 2022Determined by the planning committee
Loading map…
Scheme description
Listed Building Consent is sought for:The temporary attachment (by temporary adhesive) of one graphic vinyl on the north elevation (Level 5 balcony), and one graphic vinyl on the south elevation (Level 5 balcony) of the Royal Festival Hall, artistic exhibits on the windows of the Royal Festival hall (all temporary in nature and easily removed), projections onto the walls, the installation of artwork (unattached) on the L2 Clore Ballroom Balcony and the installation of temporary walls in the L1 Riverside entrance of the Royal Festival Hall from the 25th April to the 25th September 2022 (including installation and de-installation) in association with Summer 2022 at Southbank Centre.
Parties
Timeline
26 Jan 2022
Application submitted
14 Apr 2022
Committee decision: Approved
Supporting documents · 13
SECOND ADDENDUM13 Apr 2022View ↗
PAC REPORT13 Apr 2022View ↗
OPERATIONAL STATEMENT1 Feb 2022View ↗
EXISTING PROPOSED ELEVATION SECTION FLOOR PLANS1 Feb 2022View ↗
SOUTHBANK BBQ OPERATIONAL SAFETYDOCUMENT 20221 Feb 2022View ↗
VISITORS MANAGEMENT PLAN1 Feb 2022View ↗
LISTED BUILDING CONSENT1 Feb 2022View ↗
NOISE MANAGEMENT PLAN1 Feb 2022View ↗
DESIGN AND ACCESS STATEMENT1 Feb 2022View ↗
DELIVERY AND SERVICING PLAN1 Feb 2022View ↗
SCHEDULE 2 -OWNERS ON WHICH TO SERVE NOTICE 11 Feb 2022View ↗
COVID 19 SECURE POLICY 20221 Feb 2022View ↗
EXHIBIT SCHEDULE1 Feb 2022View ↗
View Application Page ↗
Data from the Lambeth planning register.
Summary
Reference
22/00342/LB
Ward
Type
Listed Building Consent
Applicant
Kim Schofield
Submitted
26 Jan 2022
Decision date
14 Apr 2022
Officer
Council
Decision
Approved
Decision route
Committee
How long, really
11
wks · this application
Submission → decision · 3 wks over the 8-week target
Public response
Objections
0
In support
0
Total comments
0