Development Intent
Planning AtlasKingston Upon ThamesNew Malden VillageApplication
Planning Application

25/03270/FUL

Fountain House 10 Burlington Road New Malden KT3 4NY

Full / Other PlanningNew Malden Village wardDistrict inset areas: Name: New Malden District Centre Inset
Submission
19 Dec 2025
Target
13 Mar 2026
Decision
13 Mar 2026
Outcome
Refused
Delegated decisionRefused
13 Mar 2026
Decided by Gosia Danik under delegated powers
Loading map…
Scheme description

Erection of first floor side extension with installation of photovoltaic panels to extension roof.

Why it was refused
Reason 1

The proposed first floor side extension, by reason of its siting, lack of setback from the front elevation, inappropriate roof form and use of materials, would fail to relate satisfactorily to the architectural composition of the host building and would appear as an incongruous and visually dominant addition within the street scene. The development would therefore harm the character and appearance of the host building and the surrounding area, contrary to Paragraph 135 of the National Planning Policy Framework (2024), Policy D3 of the London Plan (2021) and Policy DM10 of the Council's Core Strategy (2012).

Policies cited
National Planning Policy Framework 135
D3
DM10
NPPF
Parties
Applicant
Parveena Mistry
Timeline
19 Dec 2025
Application submitted
16 Jan 2026
Application validated
13 Mar 2026
Delegated decision: Refused
Supporting documents · 11
DECISION NOTICE - REFUSE - FUL13 Mar 2026View ↗
TP 12 01 A16 Jan 2026View ↗
TP 11 01 A16 Jan 2026View ↗
TP 10 02 A16 Jan 2026View ↗
TP 10 01 A16 Jan 2026View ↗
Application Form (No personal data)19 Dec 2025View ↗
SU 00 0119 Dec 2025View ↗
SU 11 0119 Dec 2025View ↗
SU 10 0119 Dec 2025View ↗
SU 10 0219 Dec 2025View ↗
TP 00 0119 Dec 2025View ↗
View Application Page ↗
Data from the Kingston Upon Thames planning register.
Summary
Reference
25/03270/FUL
Type
Full Application
Applicant
Parveena Mistry
Submitted
19 Dec 2025
Decision date
13 Mar 2026
Decision
Refused
Decision route
Delegated (officer)
How long, really
12
wks · this application
Submission → decision · 4 wks over the 8-week target
Public response
Objections
0
In support
0
Total comments
0