Planning Application

P/2023/0642

FELTHAM CORPORATION CENTRE PLANE TREE CRESCENT, FELTHAM, TW13 7BZ

Full / Other PlanningHanworth Park ward
Submission
27 Feb 2023
Target
9 May 2023
Decision
10 Feb 2025
Outcome
Approved
Delegated decisionApproved
10 Feb 2025
Decided by Leon Machisa under delegated powers
Loading map…
Scheme description

Outline planning permission with the details of access, appearance, landscaping, layout and scale reserved for later determination. A demolition phase and phased redevelopment (each phase being an independent act of development) comprising data centre use (B8) of up to 46,750 sqm GEA, including ancillary offices, internal plant and equipment (including flues), and substation. In addition to the above the Development will include car parking; provision of external plant and equipment (including flues); creation of servicing areas and provision of associated services, including waste, refuse, cycle storage, and lighting; and for the laying out of the buildings; routes and open spaces within th

Parties
Applicant
Not disclosed
Agent
Timeline
27 Feb 2023
Application submitted
14 Mar 2023
Application validated
10 Feb 2025
Delegated decision: Approved
Supporting documents · 97
125 of 97
P-Planning-Application-FormView ↗
P-Statement-OtherView ↗
P-Statement-OtherView ↗
P-Statement-OtherView ↗
P-Statement-OtherView ↗
P-Statement-OtherView ↗
P-Statement-OtherView ↗
P-Statement-OtherView ↗
P-Supporting-InformationView ↗
P-Planning-StatementView ↗
P-Statement-OtherView ↗
P-Statement-OtherView ↗
P-Design-and-Access-StatementView ↗
P-Design-and-Access-StatementView ↗
P-Statement-OtherView ↗
P-Statement-OtherView ↗
P-Statement-OtherView ↗
P-Transport-AssessmentView ↗
P-Transport-AssessmentView ↗
P-Statement-OtherView ↗
P-Statement-OtherView ↗
P-Statement-OtherView ↗
P-Statement-OtherView ↗
P-Statement-OtherView ↗
P-Statement-OtherView ↗
View Application Page ↗
Data from the Hounslow planning register.
Summary
Reference
P/2023/0642
Type
PO-Outline Application
Applicant
Not disclosed
Submitted
27 Feb 2023
Decision date
10 Feb 2025
Council
Decision
Approved
Decision route
How long, really
102
wks · this application
Submission → decision · 94 wks over the 8-week target