Planning Application
76546/APP/2021/2562
RIVER PINN FOOTBRIDGE EAST OF BREAKSPEAR RD S HAREFIELD
Full / Other PlanningHAREFIELD ward
Submission
28 Jun 2021
Target
4 Oct 2021
Decision
1 Oct 2021
Outcome
Approved
Delegated decisionApproved
1 Oct 2021Decided by Karl Dafe under delegated powers
Loading map…
Scheme description
Request for approval of Bringing into use under condition imposed by Schedule 17 to the High Speed Rail (London - West Midlands) Act 2017 relating to the Bringing into use of Scheduled Work No. 1/67A, consisting of a temporary bridge over the River Pinn commencing at a point 35 metres south of the b
Timeline
28 Jun 2021
Application submitted
30 Jun 2021
Application validated
1 Oct 2021
Delegated decision: Approved
View Application Page ↗
Data from the Hillingdon planning register.
Summary
Reference
76546/APP/2021/2562
Ward
Type
Planning Application
Applicant
—
Submitted
28 Jun 2021
Decision date
1 Oct 2021
Officer
Council
Decision
Approved
Decision route
—
How long, really
14
wks · this application
Submission → decision · 6 wks over the 8-week target