Planning Application
39755/APP/2023/652
HIGH VIEW FARM NEWYEARS GREEN LANE HAREFIELD
Full / Other PlanningICK/HAM & S HF/D 22 ward
Submission
6 Mar 2023
Target
21 Jun 2024
Decision
23 Mar 2024
Outcome
Approved
Delegated decisionApproved
23 Mar 2024Decided by Katie Crosbie under delegated powers
Loading map…
Scheme description
Regularisation of the existing green waste composting operations and proposed extension to the green waste open windrow compost maturation yard, construction of a storage container, site offices, welfare building, weighbridge/weighbridge offices, 2 no. leachate holding tanks, 2 no. 180kW generator s
Parties
Timeline
6 Mar 2023
Application submitted
8 Mar 2023
Application validated
23 Mar 2024
Delegated decision: Approved
Supporting documents · 66
1–25 of 66
APPLICATION FORMView ↗
LOCATION PLANView ↗
LOCATION PLANView ↗
BLOCK PLANView ↗
PHOTOGRAPHS (Supporting info)View ↗
SITE LAYOUT - PROPOSEDView ↗
SITE LAYOUT - PROPOSEDView ↗
NOISE ASSESSMENTView ↗
PROPOSED PLANView ↗
PROPOSED PLANView ↗
PROPOSED PLANView ↗
PROPOSED PLANView ↗
PROPOSED PLANView ↗
PROPOSED PLAN AMENDEDView ↗
PROPOSED PLAN AMENDEDView ↗
PLANView ↗
PLANView ↗
PLANView ↗
PLANView ↗
PLANView ↗
PLANView ↗
PLANView ↗
PLANView ↗
PLANView ↗
PLANView ↗
View Application Page ↗
Data from the Hillingdon planning register.
Summary
Reference
39755/APP/2023/652
Type
Planning Application
Applicant
—
Submitted
6 Mar 2023
Decision date
23 Mar 2024
Officer
Council
Decision
Approved
Decision route
—
How long, really
55
wks · this application
Submission → decision · 47 wks over the 8-week target