Planning Application
P/4901/21
THE HEIGHTS, 59 - 65 Lowlands Road, Harrow
Full / Other PlanningGreenhill ward
Submission
15 Dec 2021
Target
20 Dec 2023
Decision
20 Dec 2023
Outcome
Approved
Committee decisionApproved
20 Dec 2023Determined by the planning committee
Loading map…
Scheme description
Five storey front extension comprising of thirty two shared living units (Use Class Sui Generis); replacement of windows to front elevation; landscaping
Parties
Timeline
15 Dec 2021
Application submitted
22 Feb 2022
Application validated
20 Dec 2023
Committee decision: Approved
Supporting documents · 50
1–25 of 50
DN - FULL and HSE Granted2 Nov 2023View ↗
PL Proposed Basement Plan18 Jul 2022View ↗
APPAGE COMMITTEE NOTIFICATION12 Jul 2022View ↗
APPAGE COMMITTEE NOTIFICATION12 Jul 2022View ↗
PL Proposed Roof Plan6 Jul 2022View ↗
PL Supporting Documents6 Jul 2022View ↗
PL Miscellaneous Plans6 Jul 2022View ↗
PL Proposed Landscaping6 Jul 2022View ↗
PL Application Supporting Documents6 Jul 2022View ↗
PL 3D Images6 Jul 2022View ↗
PL 3D Images6 Jul 2022View ↗
PL Proposed Elevations6 Jul 2022View ↗
PL Proposed Landscaping6 Jul 2022View ↗
PL Transport Assessment Appendix A6 Jul 2022View ↗
PL Proposed Landscaping6 Jul 2022View ↗
PL Viability Report6 Jul 2022View ↗
PL Biodiversity Report6 Jul 2022View ↗
PL Daylight & Sunlight Report6 Jul 2022View ↗
PL Construction Environmental Management Plan (CEMP)6 Jul 2022View ↗
PL Design & Access Statement6 Jul 2022View ↗
PL Noise Report6 Jul 2022View ↗
PL Biodiversity Report6 Jul 2022View ↗
PL Application Supporting Documents6 Jul 2022View ↗
PL Supporting Documents9 May 2022View ↗
PL Application Incoming Letter of Objection - Redacted9 May 2022View ↗
View Application Page ↗
Data from the Harrow planning register.
Summary
Reference
P/4901/21
Ward
Type
Full Planning Application
Applicant
Low Profile Holdings
Submitted
15 Dec 2021
Decision date
20 Dec 2023
Officer
Council
Decision
Approved
Decision route
Committee
How long, really
105
wks · this application
Submission → decision · 97 wks over the 8-week target