Development Intent
Planning AtlasHarrowHeadstone SouthApplication
Planning Application

P/3934/20

77 Salisbury Road, Harrow, HA1 1NX

Full / Other PlanningHeadstone South ward
Submission
29 Oct 2020
Target
24 Mar 2021
Decision
23 Mar 2021
Outcome
Approved
Delegated decisionApproved
23 Mar 2021
Decided by WILLHO Will Hossack under delegated powers
Loading map…
Scheme description

conversion of ground floor into flat (1x2 bed) and first floor into house of multiple occupancy (hmo) for upto 4 persons; bin and cycle stores (demolition of side extension)

Parties
Timeline
29 Oct 2020
Application submitted
9 Dec 2020
Application validated
23 Mar 2021
Delegated decision: Approved
Supporting documents · 30
125 of 30
DECISION NOTICE dfugra23 Mar 2021View ↗
DECISION NOTICE dfugra23 Mar 2021View ↗
DECISION NOTICE dfugra23 Mar 2021View ↗
APPAGE COMMITTEE NOTIFICATION10 Mar 2021View ↗
APPAGE COMMITTEE NOTIFICATION10 Mar 2021View ↗
PL Proposed Ground Floor Plan26 Feb 2021View ↗
PL Proposed Sections26 Feb 2021View ↗
PL Proposed Site Plan26 Feb 2021View ↗
PL Site Plan15 Feb 2021View ↗
PL Existing Ground Floor Plan15 Feb 2021View ↗
PL Existing 1st Floor Plan15 Feb 2021View ↗
PL Existing 2nd Floor Plan15 Feb 2021View ↗
PL Existing Roof Plan15 Feb 2021View ↗
PL Existing Elevations15 Feb 2021View ↗
PL Proposed 1st Floor Plan15 Feb 2021View ↗
PL Proposed Loft Plan15 Feb 2021View ↗
PL Proposed Elevations15 Feb 2021View ↗
PL Design & Access Statement15 Feb 2021View ↗
Web Comment Public7 Jan 2021View ↗
Web Comment Public7 Jan 2021View ↗
Web Comment Public7 Jan 2021View ↗
PL Objections Incoming Correspondence - Redacted7 Jan 2021View ↗
Web Comment Public5 Jan 2021View ↗
Web Comment Public5 Jan 2021View ↗
Web Comment Public5 Jan 2021View ↗
View Application Page ↗
Data from the Harrow planning register.
Summary
Reference
P/3934/20
Type
Full Planning Application
Applicant
A Cheema
Submitted
29 Oct 2020
Decision date
23 Mar 2021
Council
Decision
Approved
Decision route
How long, really
21
wks · this application
Submission → decision · 13 wks over the 8-week target