Planning Application
P/2026/00706/FUL
Earls Court 2 Empress Approach, London, SW6 1TW
Full / Other PlanningWest Kensington ward
Submission
11 Mar 2026
Target
7 May 2026
Decision
19 May 2026
Outcome
Approved
Delegated decisionApproved
19 May 2026Decided by Sarah Knaggs under delegated powers
Loading map…
Scheme description
Installation of one additional padel court (6th padel court) with enclosures, floodlighting, and associated works, for a temporary period up to 31 December 2028; to operate in conjunction with the existing temporary 5 no. padel courts (on main site) approved under temporary planning permission (ref: 2025/03216/FUL) dated 9 April 2026.
Parties
Timeline
11 Mar 2026
Application submitted
12 Mar 2026
Application validated
19 May 2026
Delegated decision: Approved
Supporting documents · 27
1–25 of 27
ApplicationFormRedacted.pdfView ↗
2026.3.10-Planning-Letter-Padel-6th-Court----Temp-Use-Final-View ↗
Contaminated-Land-Part-1.pdfView ↗
Contaminated-Land-Part-2.pdfView ↗
FRA-Part-1.pdfView ↗
FRA-Part-2.pdfView ↗
FRA-Part-3.pdfView ↗
FRA-Part-4.pdfView ↗
LDS057_PL001_REV-B---Location-Plan.pdfView ↗
LDS057_PL002_REV-B---Existing-Site--Block-Plan.pdfView ↗
LDS057_PL031_REV-----Padel-Court-Elevations.pdfView ↗
Lighting-Impact-Assessment.pdfView ↗
Noise-Impact-Report.pdfView ↗
Layout-Plan---Existing_included_in_SiteBlock-Plan---ExistingView ↗
LDS057_PL030_REV-C---Site-SectionView ↗
LDS057_DAS_REV-B---Padel-Earl-s-CourtView ↗
LDS057_PL010_REV-E---Proposed-Site-PlanView ↗
Press-listView ↗
AMALGAMATE_SITE_NOTICEView ↗
Press-ListView ↗
PROPOSED-SITE-SECTION-AND-ELEVATIONView ↗
PROPOSED-SITE-PLANView ↗
EXISTING-SITE-PLANView ↗
LOCATION-PLANView ↗
PROPOSED-SITE-PLANView ↗
View Application Page ↗
Data from the Hammersmith And Fulham planning register.
Summary
Reference
P/2026/00706/FUL
Ward
Type
Full Planning Application
Applicant
PSC EC Limited
Submitted
11 Mar 2026
Decision date
19 May 2026
Officer
Council
Decision
Approved
Decision route
—
How long, really
10
wks · this application
Submission → decision · 2 wks over the 8-week target