Planning Application

2025/00908/DET

110 - 114 King Street London W6 0QP

Discharge of ConditionsHammersmith Broadway ward
Submission
27 Mar 2025
Target
26 Aug 2028
Decision
26 Aug 2025
Outcome
Approved
Delegated decisionApproved
26 Aug 2025
Decided by Sian Brown under delegated powers
Loading map…
Scheme description

Submission of a detailed Construction Logistics Plan, pursuant to Condition 9 of prior approval application reference: 2024/03064/PMA56 dated 26th February 2025.

Parties
Timeline
27 Mar 2025
Application submitted
28 Mar 2025
Application validated
26 Aug 2025
Delegated decision: Approved
Supporting documents · 5
P24049-CLP4-(25.03.25)View ↗
APPLICATIONFORMREDACTEDView ↗
REVISED-CLPView ↗
PER.-DETAILS-TO-MEET-COND.-FULL-OUT-APPView ↗
DELEGATED-OFFICER-REPORTView ↗
View Application Page ↗
Data from the Hammersmith And Fulham planning register.
Summary
Reference
2025/00908/DET
Type
Details to Meet Conditions Full/Outline
Applicant
TE Hammersmith Ltd
Submitted
27 Mar 2025
Decision date
26 Aug 2025
Officer
Decision
Approved
Decision route
How long, really
22
wks · this application
Submission → decision · 14 wks over the 8-week target