2021/03424/FUL

Hammersmith Hospital Du Cane Road London W12 0HS

Full / Other PlanningCollege Park And Old Oak ward
Submission
22 Oct 2021
Target
21 Dec 2025
Decision
21 Dec 2022
Outcome
Approved
Delegated decisionApproved
21 Dec 2022
Decided by Matthew Lawton under delegated powers
Loading map…
Scheme description

Installation of new external piping for the expansion of the MTHW heating network to include a new pipe bridge sitting across exterior of the Energy Centre, Gary Weston and Catherine Lewis Buildings; installation of a new flue within the existing 30m CHP mast; replacement of 6no. high level windows with ventilation louvres to the existing Energy Centre fa?ade; in connection with the replacement of one steam boiler with a new MTHW boiler in the existing Energy Centre together with the installation of a heat exchanger.

Parties
Timeline
22 Oct 2021
Application submitted
25 Oct 2021
Application validated
21 Dec 2022
Delegated decision: Approved
Supporting documents · 58
125 of 58
21-2044-PL-015-PROPOSED-ELEVS-P2View ↗
21-2044-PL-013-PROPOSED-ELEVS-P3View ↗
HAMMERSMITH-HOSPITAL-HERITAGE-AND-VISUAL-IMPACT-STATEMENTView ↗
3272---CIL_QUESTIONS-HAMMERSMITH-HOSPITALView ↗
MAIN-PIPEWORK-ROUTE_DVView ↗
PIPE-SUPPORT-21-2044-ST-110-ELEVS-T1View ↗
PIPE-SUPPORT-21-2044-ST-111-ELEVS-T1View ↗
PIPE-SUPPORT-21-2044-ST-150-DETAILS-T1View ↗
21-2044-PL-004-EXISTING-ELEVS-P2View ↗
21-2044-PL-002-EXISTING-ELEVS-P2View ↗
21-2044-PL-006-EXISTING-ELEVS-P1View ↗
21-2044-PL-014-PROPOSED-ELEVS-P2View ↗
PIPE-SUPPORT-21-2044-ST-101-LAYOUT-T1View ↗
HH---LOGISTIC-PLANView ↗
21-2044-PL-005-EXISTING-ELEVS-P2View ↗
21-2044-PL-011-PROPOSED-ELEVS-P3View ↗
PIPE-SUPPORT-21-2044-ST-100-LAYOUT-T1View ↗
IC-HEALTHCARE-AQA-OCTOBER-2021-ISSUE-3View ↗
21-2044-PL-003-EXISTING-ELEVS-P2View ↗
21-2044-PL-012-PROPOSED-ELEVS-P2View ↗
PIPE-SUPPORT-21-2044-ST-151-BRIDGES-AND-TOWER-T1View ↗
21-2044-PL-001-EXISTING-ELEVS-P2View ↗
3272---102-P2---HAMMERSMITH-HOSPITAL---SITE-PLAN(1)View ↗
3272---101-P2---HAMMERSMITH-HOSPITAL---LOCATION-PLAN(1)View ↗
HAMMERSMITH-HOSPITAL-ACOUSTIC-REPORT-FINAL-V1.3View ↗
View Application Page ↗
Data from the Hammersmith And Fulham planning register.
Summary
Reference
2021/03424/FUL
Type
Full Planning Application
Applicant
Breathe Energy Ltd
Submitted
22 Oct 2021
Decision date
21 Dec 2022
Decision
Approved
Decision route
How long, really
61
wks · this application
Submission → decision · 53 wks over the 8-week target