Planning Application
2023/1932
HOMERTON HOSPITAL Homerton Grove, Hackney, London, E9 6SR
Full / Other PlanningHomerton Ward ward
Submission
21 Aug 2023
Target
24 Nov 2023
Decision
21 Nov 2023
Outcome
Approved
Delegated decisionApproved
21 Nov 2023Decided by Erin Glancy under delegated powers
Loading map…
Scheme description
New electrical substation, replacement of existing generators and fuel tanks, and an upgrade to the existing electrical substation.
Parties
Timeline
21 Aug 2023
Application submitted
29 Sep 2023
Application validated
21 Nov 2023
Delegated decision: Approved
Supporting documents · 12
DN-Full Planning Granted Final21 Nov 2023View ↗
Officer Report14 Nov 2023View ↗
Noise-survey-and-generator-noise-assessment29 Sep 2023View ↗
-P01-Site-Plan-Existing29 Sep 2023View ↗
811505181695976903:: ::02933 P01-Site-Plan-Demolition P01 Si29 Sep 2023View ↗
P01-Site-Plan-Proposed29 Sep 2023View ↗
P01-Elevations-Existing29 Sep 2023View ↗
P01-Elevations-Proposed29 Sep 2023View ↗
P01-Design-and-Access-Statement29 Sep 2023View ↗
Community Infrastructure Levy - Completed form22 Aug 2023View ↗
The location plan22 Aug 2023View ↗
Application Form - Without Personal Data22 Aug 2023View ↗
View Application Page ↗
Data from the Hackney planning register.
Summary
Reference
2023/1932
Ward
Type
Full Planning Permission
Applicant
Ben Jugoo
Submitted
21 Aug 2023
Decision date
21 Nov 2023
Officer
Council
Decision
Approved
Decision route
Delegated (officer)
How long, really
13
wks · this application
Submission → decision · 5 wks over the 8-week target