Planning Application
2021/2341
Sorsby Medical Practice, 3 Mandeville Street, Hackney, London, E5 0DH
Full / Other PlanningKings Park Ward ward
Submission
2 Aug 2021
Target
13 Jan 2023
Decision
12 Jan 2023
Outcome
Approved
Committee decisionApproved
12 Jan 2023Determined by the planning committee
Loading map…
Scheme description
Demolition of existing building and erection of an 8 storey mixed-use building comprising commercial and/or community floorspace (use classes E/F2) and 46 residential units with associated cycle parking and refuse and recycling facilities
Parties
Timeline
2 Aug 2021
Application submitted
12 Jan 2023
Committee decision: Approved
Supporting documents · 50
1–25 of 50
Officer-Report3 Oct 2025View ↗
Completed-S106-3-Mandeville-Street-London-E5-ODH.pdf13 Jan 2023View ↗
DN-Full Planning Granted Final12 Jan 2023View ↗
3-Mandeville-Street-E5-FVA-Review-November-211 Apr 2022View ↗
Mandeville-Summary-report-Final30 Mar 2022View ↗
1-656-WTA-XX-08-DR-A-1008-P02_125 Feb 2022View ↗
1-656-MandevilleStreet-AdjustedRoofCores-22010725 Feb 2022View ↗
1-656-Drawing-ListPlanning-21122225 Feb 2022View ↗
777-FH-XX-01-DP-L-101-General-Arrangement-Plan-P425 Feb 2022View ↗
777-FH-RP-02-Urban-Greening-Factor25 Feb 2022View ↗
1-656-WTA-XX-ZZ-DR-A-1305-P02_125 Feb 2022View ↗
1-656-WTA-XX-ZZ-DR-A-1202-P02_1.25 Feb 2022View ↗
1-656-WTA-XX-ZZ-DR-A-1200-P02_125 Feb 2022View ↗
1-656-WTA-XX-09-DR-A-1009-P02_125 Feb 2022View ↗
Fire-Strategy-Statement10 Dec 2021View ↗
EA-Response-compressed10 Dec 2021View ↗
Fire-Statement-Form10 Dec 2021View ↗
Application Form - Without Personal Data3 Aug 2021View ↗
Planning statement3 Aug 2021View ↗
Covering letter3 Aug 2021View ↗
Floor Plans3 Aug 2021View ↗
Floor Plans23 Aug 2021View ↗
Floor Plan 33 Aug 2021View ↗
Floor plans 43 Aug 2021View ↗
Floor Plans 53 Aug 2021View ↗
View Application Page ↗
Data from the Hackney planning register.
Summary
Reference
2021/2341
Ward
Type
Full Planning Permission
Applicant
Pocket Living Mandeville Street Ltd
Submitted
2 Aug 2021
Decision date
12 Jan 2023
Officer
Council
Decision
Approved
Decision route
Committee
How long, really
75
wks · this application
Submission → decision · 67 wks over the 8-week target