Development Intent
Planning AtlasGreenwichGREENWICH PARKApplication
Planning Application

26/0630/HD

14 CROOMS HILL, GREENWICH, LONDON, SE10 8ER

HouseholderGREENWICH PARK ward
Submission
27 Feb 2026
Target
24 Apr 2026
Decision
8 May 2026
Outcome
Approved
Delegated decisionApproved
8 May 2026
Decided by Amelia Elliott under delegated powers
Loading map…
Scheme description

Removal of the non-original side garage, construction of a new replacement garage; excavate the existing brick basement vault, extend the existing basement to the rear and rebuild/repair, introducing two brick vaults to connect to existing; construction of new basement level under existing north wing to house plant and services equipment for Air Source Heat Pump and Water Tank; single storey rear extension beyond the reconstructed garage; removal of the existing outbuildings to the rear to accommodate a single storey structure; installation of lightweight glazed roof over part of stepped roof of north wing; internal alterations and associated plant; introduction of an Air Source Heat pump an

Parties
Applicant
Not disclosed
Timeline
27 Feb 2026
Application submitted
8 May 2026
Delegated decision: Approved
Supporting documents · 39
125 of 39
Reports8 May 2026View ↗
Decision notice8 May 2026View ↗
Proposed pergola elevations17 Apr 2026View ↗
Proposed wall opening to ground floor of main house10 Apr 2026View ↗
Correspondance10 Mar 2026View ↗
Archaeological desk based assessment part 32 Mar 2026View ↗
Archaeological desk based assessment part 42 Mar 2026View ↗
Archaeological desk based assessment part 52 Mar 2026View ↗
Archaeological desk based assessment part 62 Mar 2026View ↗
Application form redacted2 Mar 2026View ↗
Drawing pack2 Mar 2026View ↗
Archaeological desk based assessment2 Mar 2026View ↗
Archaeological desk based assessment part 22 Mar 2026View ↗
Planning statement2 Mar 2026View ↗
Covering letter2 Mar 2026View ↗
Lath and plaster method statement2 Mar 2026View ↗
Schedule of works2 Mar 2026View ↗
Tanking method statement2 Mar 2026View ↗
Heritage design and access report part 12 Mar 2026View ↗
Project aims and basement stratgey2 Mar 2026View ↗
Project aims and basement strategy part 22 Mar 2026View ↗
Preliminary unexplored ordnance risk assessment2 Mar 2026View ↗
Landscape proposal2 Mar 2026View ↗
Arboricultural impact assessment2 Mar 2026View ↗
Structural method statement2 Mar 2026View ↗
View Application Page ↗
Data from the Greenwich planning register.
Summary
Reference
26/0630/HD
Type
Householders
Applicant
Not disclosed
Submitted
27 Feb 2026
Decision date
8 May 2026
Council
Decision
Approved
Decision route
Delegated (officer)
How long, really
10
wks · this application
Submission → decision · 2 wks over the 8-week target
Public response
Objections
2
In support
3
Total comments
5