24/3095/F

Land adjacent 81-88 Beresford Street, Woolwich, SE18 6BG

Full / Other PlanningWOOLWICH ARSENAL wardNot Available
Submission
25 Sep 2024
Target
25 Dec 2024
Decision
7 Apr 2025
Outcome
Approved
Committee decisionApproved
7 Apr 2025
Determined by the planning committee
Loading map…
Scheme description

Construction of a new building comprising purpose-built student accommodation and associated amenity space (Sui Generis) as an extension of the purpose built student accommodation at 81-88 Beresford Street, together with ancillary plant and servicing; and associated enabling works. Further detailed explanation of the proposal for consultation purposes (not forming part of the formal description of development set out above): Construction of a new part 11,part 12 storey building with roof canopy and associated amenity space comprising 120 purpose-built student accommodation units (Sui Generis) as an extension of the purpose built student accommodation at 81-88 Beresford Street (Sui Generis),

Parties
Applicant
RA Student Limited
Timeline
25 Sep 2024
Application submitted
7 Apr 2025
Committee decision: Approved
Supporting documents · 71
125 of 71
Decision notice7 Apr 2025View ↗
Beresford street phase 2 - foul water capacity pre-planning 21 Oct 2024View ↗
Updated17 Oct 2024View ↗
Updated17 Oct 2024View ↗
Lpg wlca assessment_planning_beresford p0117 Oct 2024View ↗
Gla ces assessment_planning_beresford p0117 Oct 2024View ↗
Gla spreadsheet17 Oct 2024View ↗
Acknowledgement letter14 Oct 2024View ↗
Gla circular economy11 Oct 2024View ↗
Gla spreadsheet11 Oct 2024View ↗
Biodiversity net gain assessment memo25 Sep 2024View ↗
Air quality assessment25 Sep 2024View ↗
Circular economy statement25 Sep 2024View ↗
Delivery and servicing plan25 Sep 2024View ↗
Breeam assessment technical note25 Sep 2024View ↗
Archaeological desktop assessment25 Sep 2024View ↗
Design & access statement part 125 Sep 2024View ↗
Draft construction management plan and construction logistic25 Sep 2024View ↗
Design & access statement part 225 Sep 2024View ↗
Flood risk assessment, suds & drainage strategy25 Sep 2024View ↗
Energy and sustainability assessment25 Sep 2024View ↗
Daylight & sunlight report25 Sep 2024View ↗
Geoenvironmental and geotechnical assessment part 125 Sep 2024View ↗
Geoenvironmental and geotechnical assessment part 325 Sep 2024View ↗
Geoenvironmental and geotechnical assessment part 225 Sep 2024View ↗
View Application Page ↗
Data from the Greenwich planning register.
Summary
Reference
24/3095/F
Type
Full Planning Permission
Applicant
RA Student Limited
Submitted
25 Sep 2024
Decision date
7 Apr 2025
Council
Decision
Approved
Decision route
Committee
How long, really
28
wks · this application
Submission → decision · 20 wks over the 8-week target
Public response
Objections
8
In support
1
Total comments
9