SILVERTOWN TUNNEL, LONDON SE10

Full / Other PlanningPENINSULA - NO LONGER EXISTS ward
Submission
24 Feb 2022
Target
21 Apr 2022
Decision
26 Apr 2022
Outcome
Approved
Delegated decisionApproved
26 Apr 2022
Decided by Hoa Vong under delegated powers
Loading map…
Scheme description

The Silvertown Tunnel Order 2018 ('the Order'), formal application for approval of a Construction Traffic Management Plan (CTMP), for main construction works in Greenwich from April 2022 to March 2023 ? made under Schedule 2 of the Order to partially discharge Requirement at Paragraph 5(3)(e).

Parties
Applicant
Tim Snell
Agent
Officer
Hoa Vong
Timeline
24 Feb 2022
Application submitted
26 Apr 2022
Delegated decision: Approved
Supporting documents · 5
Officers delegated report26 Apr 2022View ↗
Decision notice26 Apr 2022View ↗
Cover letter4 Mar 2022View ↗
Acknowledgement letter4 Mar 2022View ↗
Worksite specific construction traffic management plan25 Feb 2022View ↗
View Application Page ↗
Data from the Greenwich planning register.
Summary
Reference
22/0719/G
Type
Development by Govt Dept/Stat.Und.
Applicant
Tim Snell
Submitted
24 Feb 2022
Decision date
26 Apr 2022
Officer
Council
Decision
Approved
Decision route
Delegated (officer)
How long, really
9
wks · this application
Submission → decision · 1 wks over the 8-week target
Public response
Objections
7
In support
0
Total comments
7