23/00824/FUL

Heritage House 345 Southbury Road Enfield EN1 1TW

Full / Other PlanningPonders End wardContaminated Land: Site Description: LEAD/STEEL and AL Site
Submission
13 Mar 2023
Target
12 Jun 2023
Decision
4 Mar 2024
Outcome
Approved
Committee decisionApproved
4 Mar 2024
Determined by the planning committee
Loading map…
Scheme description

Full planning application for the demolition of the existing buildings and redevelopment for a multi-level logistics building (Use Classes E(g)(iii), B2 and B8) capable of subdivision and commercial, business and service buildings (Use Classes E, B2 and B8) including boundary treatment, landscaping, car parking, servicing, public realm and associated works.

Parties
Applicant
Not disclosed
Timeline
13 Mar 2023
Application submitted
4 Mar 2024
Committee decision: Approved
Supporting documents · 135
125 of 135
Decision Notice4 Mar 2024View ↗
PRESS NOTICE 29.3.2318 Oct 2023View ↗
127B8 Sep 2023View ↗
Flood Risk Assessment & Sustainable Drainage Strategy15 Aug 2023View ↗
Committee Report18 Jul 2023View ↗
CBRE Public Comments Response Letter11 Jul 2023View ↗
Drawing Schedule_Updated 13.06.202313 Jun 2023View ↗
GLA WHOLE LIFE-CYCLE CARBON (WLC) ASSESSMENT TEMPLATE dated 9 Jun 2023View ↗
CBRE Design Response Letter_Issue 08.06.20238 Jun 2023View ↗
17531 - 129A Proposed Elevations - Main Logistics Unit8 Jun 2023View ↗
17531 - 128A Proposed Site Sections8 Jun 2023View ↗
17531 - 126B Proposed Roof Level Plan8 Jun 2023View ↗
17531 - 125A Proposed First Floor Mezzanine Plan8 Jun 2023View ↗
17531 - 124B Proposed First Floor Plan8 Jun 2023View ↗
17531 - 123A Proposed Ground Floor Mezzanine Plan8 Jun 2023View ↗
17531 - 122A Proposed Mezzanine Level Plan - CBS Buildings8 Jun 2023View ↗
17531 - 121A Proposed Ground Floor Plan - CBS Buildings8 Jun 2023View ↗
17531 - 120B Proposed Ground Floor Plan8 Jun 2023View ↗
17531 - 119B Proposed Block Plan8 Jun 2023View ↗
0290-INSIG-RP-MEP-10-(05)7 Jun 2023View ↗
0290-INSIG-RP-MEP-10-(05)7 Jun 2023View ↗
I&L Response to LBE Watercourses email 23.06.011 Jun 2023View ↗
Transport Technical Note dated May 202330 May 2023View ↗
DRAINAGE TECHNICAL NOTE UPDATED 30.05.2023 INCLUDING DWG NO.30 May 2023View ↗
I&L RESPONSE TO LBE WATERCOURSES30 May 2023View ↗
View Application Page ↗
Data from the Enfield planning register.
Summary
Reference
23/00824/FUL
Type
Full
Applicant
Not disclosed
Submitted
13 Mar 2023
Decision date
4 Mar 2024
Council
Decision
Approved
Decision route
Committee
How long, really
51
wks · this application
Submission → decision · 43 wks over the 8-week target
Public response
Objections
0
In support
0
Total comments
0