Planning Application
21/01816/FUL
The Royal Chace Hotel The Ridgeway Enfield EN2 8AR
Full / Other PlanningDevelopment Control teams: Area: NORTH Code: DCAREA_N
Submission
10 May 2021
Target
24 Sep 2021
Decision
10 May 2022
Outcome
Approved
Committee decisionApproved
10 May 2022Determined by the planning committee
Loading map…
Scheme description
Redevelopment of site involving demolition of existing hotel and erection of a three-storey care-home (C2 use) with 92 rooms and 64 residential dwellings.
Parties
Timeline
10 May 2021
Application submitted
25 Jun 2021
Application validated
10 May 2022
Committee decision: Approved
Supporting documents · 166
1–25 of 166
S106 Agreement1 Feb 2024View ↗
Planning committee report24 Oct 2022View ↗
Planning committee report24 Oct 2022View ↗
Planning committee report24 Oct 2022View ↗
Planning committee report24 Oct 2022View ↗
Planning committee report24 Oct 2022View ↗
Planning committee report24 Oct 2022View ↗
Planning committee report24 Oct 2022View ↗
Planning committee report24 Oct 2022View ↗
Planning committee report24 Oct 2022View ↗
Planning committee report24 Oct 2022View ↗
Planning committee report24 Oct 2022View ↗
Planning committee report24 Oct 2022View ↗
Planning committee report24 Oct 2022View ↗
Decision Notice10 May 2022View ↗
PRESS NOTICE 8.12.218 Dec 2021View ↗
Press Notice 8.12.21 dc8 Dec 2021View ↗
Affordable Housing Statement (December 2021)7 Dec 2021View ↗
Royal Chace Care Home-Landscape (Ref B21004-101K)7 Dec 2021View ↗
Proposed Care home section (Ref AA6946-2016)2 Dec 2021View ↗
Drainage Strategy Report (Dated Oct 21)2 Dec 2021View ↗
Updated Ecological Appraisal (Dated Oct 21)2 Dec 2021View ↗
Updated Energy Strategy (Dated Oct 21)2 Dec 2021View ↗
Revised Landscape Proposals (Rev G)2 Dec 2021View ↗
Building height layout plan (Ref 062001-BEL-NL-03- Rev D)1 Dec 2021View ↗
View Application Page ↗
Data from the Enfield planning register.
Summary
Reference
21/01816/FUL
Ward
—
Type
Full
Applicant
Signature/Bellway
Submitted
10 May 2021
Decision date
10 May 2022
Officer
Council
Decision
Approved
Decision route
Committee
How long, really
52
wks · this application
Submission → decision · 44 wks over the 8-week target
Public response
Objections
1
In support
0
Total comments
1