20/01021/FUL

ARK John Keats Academy 52 Bell Lane EN3 5PA

Full / Other PlanningEnfield Highway wardDevelopment Control teams: Area: NORTH Code: DCAREA_N
Submission
25 Mar 2020
Target
14 Aug 2020
Decision
2 Oct 2020
Outcome
Approved
Committee decisionApproved
2 Oct 2020
Determined by the planning committee
Loading map…
Scheme description

Erection of 3 storey teaching block within existing courtyard and 2 storey temporary teaching block located on the MultiUse Games Area and Temporary Site Entrance on Bell Lane.

Parties
Applicant
Mrs Hannah Peat
Timeline
25 Mar 2020
Application submitted
15 May 2020
Application validated
2 Oct 2020
Committee decision: Approved
Supporting documents · 27
125 of 27
COMMITTEE amendments5 Oct 2020View ↗
Decision Notice2 Oct 2020View ↗
Landscaping30 Sep 2020View ↗
Landscaping30 Sep 2020View ↗
Press Notice21 Jul 2020View ↗
Ark John Keats Academy - Energy Statement28 Apr 2020View ↗
BREEAM Pre-Assessment Report28 Apr 2020View ↗
Health Impact Assessment28 Apr 2020View ↗
Be Lean BRUKL28 Apr 2020View ↗
Be Lean BRUKL28 Apr 2020View ↗
Be Lean BRUKL28 Apr 2020View ↗
SuDS report28 Apr 2020View ↗
Block plan of the site25 Mar 2020View ↗
The location plan25 Mar 2020View ↗
EXISTING FIRST FLOOR PLAN25 Mar 2020View ↗
PROPOSED SITE PLAN25 Mar 2020View ↗
TEMPORARY ACCOMMODATION AND SITE SET UP PLAN25 Mar 2020View ↗
LANDSCAPING PROPOSALS25 Mar 2020View ↗
SECTION DRAWINGS25 Mar 2020View ↗
FLOOR PLANS AND ELEVATIONS25 Mar 2020View ↗
SECOND FLOOR AND ROOF PLAN25 Mar 2020View ↗
PROPOSED GROUND AND FIRST FLOOR PLAN25 Mar 2020View ↗
PROPOSED ELEVATIONS25 Mar 2020View ↗
ELEVATIONS B AND D25 Mar 2020View ↗
ELEVATION A AND C25 Mar 2020View ↗
View Application Page ↗
Data from the Enfield planning register.
Summary
Reference
20/01021/FUL
Type
Full
Applicant
Mrs Hannah Peat
Submitted
25 Mar 2020
Decision date
2 Oct 2020
Council
Decision
Approved
Decision route
Committee
How long, really
27
wks · this application
Submission → decision · 19 wks over the 8-week target
Public response
Objections
0
In support
0
Total comments
0