Development Intent
Planning AtlasEalingSouthall GreenApplication
Planning Application

260409CND

13 - 19 The Green Southall UB2 4AH

Discharge of ConditionsSouthall Green wardBuilding Of Facade Group Value: Name: Bank at 11a The Green
Submission
3 Feb 2026
Target
31 Mar 2026
Decision
20 Apr 2026
Outcome
Approved
Delegated decisionApproved
20 Apr 2026
Decided by Cathy Munonyedi under delegated powers
Loading map…
Scheme description

Details of Construction Management Plan (Stage 2) pursuant to condition 7 of planning permission ref: 243547FUL dated 13/03/2025 for: Construction of 23 storey building, with a basement level, to be used as student accommodation (Use Class Sui Generis), provision of associated cycle storage, refuse storage facilities, amenity space, public realm, landscaping and associated works

Parties
Applicant
Tide Construction
Timeline
3 Feb 2026
Application submitted
20 Apr 2026
Delegated decision: Approved
Supporting documents · 5
DECISION NOTICE20 Apr 2026View ↗
OFFICERS REPORT20 Apr 2026View ↗
APPLICATIONFORMREDACTED3 Feb 2026View ↗
LET-COND 7 - HM 3.2.263 Feb 2026View ↗
R06-SHS-STAGE 2 CONSTRUCTION LOGISTICS PLAN-FINAL3 Feb 2026View ↗
View Application Page ↗
Data from the Ealing planning register.
Summary
Reference
260409CND
Type
Discharge Condition
Applicant
Tide Construction
Submitted
3 Feb 2026
Decision date
20 Apr 2026
Council
Decision
Approved
Decision route
Delegated (officer)
How long, really
11
wks · this application
Submission → decision · 3 wks over the 8-week target
Public response
Objections
0
In support
0
Total comments
0