Development Intent
Planning AtlasEalingNorth ActonApplication
Planning Application

244851FUL

46 Highfield Road Acton W3 0AL

Full / Other PlanningNorth Acton wardCrossrail 106 Legal Agreements: Description: Application wit
Submission
19 Dec 2024
Target
13 Feb 2025
Decision
10 Nov 2025
Outcome
Approved
Delegated decisionApproved
10 Nov 2025
Decided by Silindile Khumalo under delegated powers
Loading map…
Scheme description

Construction of a four x two storey (with habitable roof space), dwellinghouses and provision of associated private amenity space, off-street parking, refuse and cycle storage (following demolition of the existing dwelling, integrated double garage and outbuilding)

Parties
Applicant
Mr K Sagar
Timeline
19 Dec 2024
Application submitted
10 Nov 2025
Delegated decision: Approved
Supporting documents · 20
FINAL DECISION NOTICE10 Nov 2025View ↗
LEGAL AGREEMENT10 Nov 2025View ↗
OFFICERS REPORT14 Apr 2025View ↗
DRAFT DECISION NOTICE14 Apr 2025View ↗
NEIGHBOUR SITE NOTICE10 Jan 2025View ↗
244851FUL SITE NOTICE MAP SN X 6.PDF10 Jan 2025View ↗
APPLICATIONFORMREDACTED19 Dec 2024View ↗
23-039 - EXISTING DRAWINGS19 Dec 2024View ↗
23-039 - PROPOSED DRAWINGS19 Dec 2024View ↗
23-039 - ARBORICULTURAL IMPACT ASSESSMENT19 Dec 2024View ↗
23-039 - LANDSCAPE MANAGEMENT19 Dec 2024View ↗
23-039 - LANDSCAPE MASTERPLAN19 Dec 2024View ↗
23-039 - LANDSCAPE STRATEGY19 Dec 2024View ↗
23-039 - LANDSCAPING ROOF PLAN19 Dec 2024View ↗
23-039 - UGF CALCULATION19 Dec 2024View ↗
23-039 - TRANSPORT STATEMENT19 Dec 2024View ↗
23-039 - CONSTRUCTION MANAGEMENT PLAN19 Dec 2024View ↗
23-039 - BNG METRIC EXTRACTS19 Dec 2024View ↗
23-039 - BNG STATEMENT19 Dec 2024View ↗
23-039 - PLANNING DESIGN AND ACCESS STATEMENT19 Dec 2024View ↗
View Application Page ↗
Data from the Ealing planning register.
Summary
Reference
244851FUL
Type
Full Application
Applicant
Mr K Sagar
Submitted
19 Dec 2024
Decision date
10 Nov 2025
Council
Decision
Approved
Decision route
Delegated (officer)
How long, really
47
wks · this application
Submission → decision · 39 wks over the 8-week target
Public response
Objections
13
In support
0
Total comments
13