Planning Application
241451FUL
27-29 The Broadway Southall UB1 1JY
Full / Other PlanningSouthall Broadway wardArchaeological Interest Area: Name: High Street, Southall De
Submission
26 Mar 2024
Target
21 May 2024
Decision
4 Dec 2024
Outcome
Approved
Delegated decisionApproved
4 Dec 2024Decided by James Maloney under delegated powers
Loading map…
Scheme description
Reconfiguration of ground floor to provide commercial/office space (Use Class E g(i)); conversion of upper floors into 8 self-contained flats (Use Class C3), facilitated by the construction of a 3rd floor, associated external alterations and provision of associated cycle storage and refuse storage facilities
Parties
Timeline
26 Mar 2024
Application submitted
4 Dec 2024
Delegated decision: Approved
Supporting documents · 26
1–25 of 26
LEGAL AGREEMENT4 Dec 2024View ↗
FINAL DECISION NOTICE4 Dec 2024View ↗
DRAFT DECISION NOTICE2 Aug 2024View ↗
OFFICERS REPORT2 Aug 2024View ↗
AMENDED PROPOSED ELEVATION E431 Jul 2024View ↗
AMENDED PROPOSED GF FF PLAN31 Jul 2024View ↗
AMEDNED PROPOSED 2 AND 3 FLOOR PLAN31 Jul 2024View ↗
AMENDED PROPOSED SECTION31 Jul 2024View ↗
AMENDED PROPOSED ELEVATION E231 Jul 2024View ↗
AMENDED PROPOSED ELEVATION E131 Jul 2024View ↗
AMENDED PROPOSED ELEVATION E331 Jul 2024View ↗
NEIGHBOUR SITE NOTICE15 Apr 2024View ↗
SITE NOTICE MAP15 Apr 2024View ↗
PROPOSED ELEVATION E126 Mar 2024View ↗
SITE PLAN26 Mar 2024View ↗
DAS26 Mar 2024View ↗
LOCATION PLAN26 Mar 2024View ↗
APPLICATION26 Mar 2024View ↗
EXISTING 1ST FLOOR PLAN26 Mar 2024View ↗
EXISTING 2ND FLOOR PLAN26 Mar 2024View ↗
EXISTING GR FLOOR PLAN26 Mar 2024View ↗
EXISTING ELEVATION E226 Mar 2024View ↗
EXISTING ELEVATION26 Mar 2024View ↗
EXISTING SECTIONS26 Mar 2024View ↗
EXISTING ELEVATION E"26 Mar 2024View ↗
View Application Page ↗
Data from the Ealing planning register.
Summary
Reference
241451FUL
Type
Full Application
Applicant
Mr C
Submitted
26 Mar 2024
Decision date
4 Dec 2024
Officer
Council
Decision
Approved
Decision route
Delegated (officer)
How long, really
36
wks · this application
Submission → decision · 28 wks over the 8-week target
Public response
Objections
0
In support
0
Total comments
0