201379OUT

TfL Landholdings At Bollo Lane Acton Ealing Bounded By The Railway Lines To The West Acton Town Station To The North Bollo Lane To The East And The Bollo Lane Level Crossing To The South. London W3 8QU

Full / Other PlanningSouth Acton wardArchaeological Interest Area: Name: Avenue Gardens/Heathfiel
Submission
20 Mar 2020
Target
17 Sep 2020
Decision
22 Dec 2021
Outcome
Approved
Committee decisionApproved
22 Dec 2021
Loading map…
Scheme description

Hybrid planning application for comprehensive phased redevelopment of the site comprising: Full planning permission for demolition of existing buildings and structures (Phases 1 to 2) to provide up to 550sqm (GIA) of Business Use Class B1a/b/c floorspace, up to 125sqm (GIA) of flexible commercial Use Classes A1 / A2 / A3 / A4 / A5, up to 200 new affordable and market dwellings in a block up to 25 storeys, replacement Train Crew Accommodation (TCA) building, new footway to Bollo Lane, relocated bus stop, new pedestrian crossing, new open and amenity space and associated public realm works. Outline planning permission (Phases 3 to 4) for demolition of existing buildings and structures to provi

Parties
Applicant
Not disclosed
Officer
Timeline
20 Mar 2020
Application submitted
18 Jun 2020
Application validated
22 Dec 2021
Committee decision: Approved
Supporting documents · 288
125 of 200
DECISION NOTICE13 Jan 2022View ↗
S10613 Jan 2022View ↗
GLA STAGE 2 REPORT & LETTER23 Nov 2021View ↗
GLA STAGE 2 REPORT & LETTER23 Nov 2021View ↗
OBJECTION HOUNSLOW COUNCILLOR JOANNA BIDDULPH20 Jan 2021View ↗
102 BOLLO LANE STATEMENT20 Jan 2021View ↗
PETITION19 Jan 2021View ↗
TVIA ADDENDUM KEW VIEW W DECEMBER 202017 Dec 2020View ↗
TFLBL-HOK-2Z-DR-A-1023REV2 AMENDED PLAN9 Dec 2020View ↗
TFLBL-HOK-BL-00-A-1050 ADDITIONAL PLAN9 Dec 2020View ↗
DESIGN CODE ADDENDUM3 Dec 2020View ↗
CIRCULAR ECONOMY REPORT2 Dec 2020View ↗
HEIGHT AND MASSING NOTE, NOVEMBER 202027 Nov 2020View ↗
NEIGHBOUR RESPONSE25 Sep 2020View ↗
NEIGHBOUR21 Sep 2020View ↗
TVIA ADDENDUM SEPT 202021 Sep 2020View ↗
- BIODIVERSITY TECHNICAL NOTE21 Sep 2020View ↗
UGF REPORT21 Sep 2020View ↗
GREEN SPACE ECOLOGY & TREE PLANTING 1 & 221 Sep 2020View ↗
GREEN SPACE ECOLOGY & TREE PLANTING 1 & 221 Sep 2020View ↗
OBJECTION EMAIL24 Aug 2020View ↗
RESTART SURVEY23 Jul 2020View ↗
CONSULTATION RESPONSE8 Jul 2020View ↗
MAJOR SITE NOTICE19 Jun 2020View ↗
SITE NOTICE MAP19 Jun 2020View ↗

Showing 200 of 288 documents on record.

View Application Page ↗
Data from the Ealing planning register.
Summary
Reference
201379OUT
Type
Hybrid Application
Applicant
Not disclosed
Submitted
20 Mar 2020
Decision date
22 Dec 2021
Officer
Council
Decision
Approved
Decision route
Committee
How long, really
92
wks · this application
Submission → decision · 84 wks over the 8-week target
Public response
Objections
636
In support
10
Total comments
653