Planning Application
20/00769/LBC
Philpot House 2-3 Philpot Lane London EC3M 8AN
Listed BuildingBridge And Bridge Without ward
Submission
8 Oct 2020
Target
3 Dec 2020
Decision
30 Sep 2021
Outcome
Approved
Committee decisionApproved
30 Sep 2021Determined by the planning committee
Loading map…
Scheme description
Demolition of chimney attached to Grade II Listed 2 and 3 Philpot Lane.
Parties
Timeline
8 Oct 2020
Application submitted
30 Sep 2021
Committee decision: Approved
Supporting documents · 30
1–25 of 30
LISTED BUILDING CONSENT (CONDITIONAL)30 Sep 2021View ↗
OFFICER'S REPORT30 Sep 2021View ↗
DRAWING ISSUE SHEET4 Jan 2021View ↗
EXISTING, DEMOLITION & PROPOSED - ROOF PLAN11 Dec 2020View ↗
EXISTING, DEMOLITION & PROPOSED - LEVEL 05 PLAN11 Dec 2020View ↗
EXISTING, DEMOLITION & PROPOSED - LEVEL 04 PLAN11 Dec 2020View ↗
EXISTING, DEMOLITION & PROPOSED - LEVEL 03 PLAN11 Dec 2020View ↗
EXISTING, DEMOLITION & PROPOSED - LEVEL 02 PLAN11 Dec 2020View ↗
EXISTING, DEMOLITION & PROPOSED - LEVEL 01 PLAN11 Dec 2020View ↗
EXISTING, DEMOLITION & PROPOSED - GROUND FLOOR PLAN11 Dec 2020View ↗
SITE NOTICE22 Oct 2020View ↗
SITE LOCATION PLAN8 Oct 2020View ↗
EXISTING ELEVATION - SOUTH8 Oct 2020View ↗
EXISTING ELEVATION - WEST8 Oct 2020View ↗
PROPOSED ELEVATION - SOUTH8 Oct 2020View ↗
DEMOLITION ELEVATION - WEST8 Oct 2020View ↗
DEMOLITION ELEVATION - SOUTH8 Oct 2020View ↗
PROPOSED ELEVATION - WEST8 Oct 2020View ↗
EXISTING ELEVATION - NORTH8 Oct 2020View ↗
PROPOSED ELEVATION - NORTH8 Oct 2020View ↗
DEMOLITION ELEVATION - NORTH8 Oct 2020View ↗
HERITAGE STATEMENT FOR LISTED BUILDING CONSENT PART 38 Oct 2020View ↗
HERITAGE STATEMENT FOR LISTED BUILDING CONSENT PART 28 Oct 2020View ↗
HERITAGE STATEMENT FOR LISTED BUILDING CONSENT8 Oct 2020View ↗
DESIGN STATEMENT LISTED BUILDING CONSENT8 Oct 2020View ↗
View Application Page ↗
Data from the City Of London planning register.
Summary
Reference
20/00769/LBC
Type
Listed Building Consent
Applicant
Mighty Oasis International Limited
Submitted
8 Oct 2020
Decision date
30 Sep 2021
Officer
Council
Decision
Approved
Decision route
Committee
How long, really
51
wks · this application
Submission → decision · 43 wks over the 8-week target
Public response
Objections
0
In support
0
Total comments
0